44活动地板作业指导书版.docx
《44活动地板作业指导书版.docx》由会员分享,可在线阅读,更多相关《44活动地板作业指导书版.docx(12页珍藏版)》请在冰点文库上搜索。
44活动地板作业指导书版
第3部分:
变电土建
活动地板作业指导书
编码:
BDTJ-ZW-14
目次
1适用范围························································································································································99
2编写依据························································································································································99
3作业流程························································································································································99
4工作前安全风险辨析及控制措施··············································································································100
5作业准备······················································································································································100
6作业方法······················································································································································101
7质量控制措施及检验标准··························································································································102
1适用范围
适用于110~500kV电网工程房屋建筑室内地面活动地板的铺设。
2编写依据
表2-1编写依据
序号
引用资料名称
1
GB50300—2001《建筑工程施工质量验收统一标准》
2
GB50209—2010《建筑地面工程施工质量验收规范》
3
GB50210—2001《建筑装饰装修工程质量验收规范》
4
DL/T5201.1—2005《电力建设施工质量验收及评定规程》第1部分:
土建工程
5
《10kV~500kV输变电及配电工程质量验收与评定标准第3部分:
变电土建工程》
6
Q/CSG11105—2008《南方电网工程施工工艺控制规范》
7
工程设计图纸、施工组织设计(方案)等技术文件
3作业流程
作业(工序)流程图见图3-1。
图3-1作业(工序)流程图
4安全风险辨析及预控
4.1活动地板作业前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。
4.2按《指南》中与活动地板作业相关联的《电网建设安全施工作业票》(编码:
BDTJ-ZW-12~19-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施
工负责人签发。
4.3施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人员负责将安全措施落实到各作业任务和步骤中。
4.4安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须重新
办理作业票,在工作完成后上交项目部保存备查。
表4-1作业任务安全基准风险指南
序号
危害名称
风险种类
风险等级
风险控制措施
1
无安全措施的焊接作业
火灾
可接受的风险
支柱焊接作业前,灭火器材应该一次性配备足够,并经项目部安全员检查满足作业要求后方可作业
2
漏电的设备
触电
低风险
切割机使用前外壳必须接地,防止触电伤人
3
未佩戴防护用品
打击
可接受的风险
使用砂浆机、切割机等必须正确佩戴安全防护用品,安全员负责监督落实
4
防护不严的洞口
坠落
可接受的风险
安全员检查防护措施的落实,如发现不符合要求的应该马上进行整改
5作业准备
5.1人员配备
表5-1人员配备表
工序名称
建议工作人数
负责人数
监护人数
基层处理
支柱(架)定位及水平控制
支柱(架)安装
铺设活动地板
清擦和打蜡
注:
作业人数根据具体工程量规模配备。
5.2主要工器具及仪器仪表配置
表5-2主要工器具及仪器仪表配置表
序号
名称
规格/编号
单位
数量
备注
1
吸盘
个
2
切割锯
台
3
手刨
台
4
螺机
台
5
水准仪
台
6
水平尺
把
7
方尺
把
8
钢尺
把
9
靠尺板
2~3m
把
注:
主要工器具及仪器仪表根据具体工程量规模配备。
6作业方法
6.1基层处理铺设活动地板面层的基层已完成,基层表面应平整、干净、不起灰。
6.2支柱(架)定位及水平控制
6.2.1在墙面500mm处设置水平标高线,在四周墙面上弹出面层标高水平控制线,并按选定的铺设方向和顺序设基准点。
6.2.2找中、套方、分格、弹线
1)首先量测房间的长、宽尺寸,找出纵横线中心交点。
当房间是矩形时,用方尺量测相邻的墙体
是否垂直,如互相不垂直,应预先对墙面进行处理,避免在安装活动板块时,在靠墙处出现楔形板块。
2)根据已量测好的平面长、宽尺寸进行计算,如果不符合活动板块模数时,依据已找好的纵横中线交点,进行对称分格,考虑将非整块板放在室内靠墙处,在基层表面上按板块尺寸弹线并形
成方格网,标出地板块安装位置和高度(标在四周墙上),并标明设备预留部位。
此项工作必须认真细致,做到方格控制线尺寸准确(此时应插入铺设活动地板下的管线,操作时要注意避开
已弹好支架底座的位置)。
3)在基层上,按设计图纸的要求弹出支柱(架)定位方格十字线,测量底座水平标高,同时在墙上四周测好支柱(架)水平控制线。
6.2.3在基层表面要标出板块的安装位置,并标明设备和电缆走向的预留位置。
6.3支柱(架)安装安装支座和横梁组件,检查复核已弹在四周墙上的标高控制线,确定安装基准点,然后按基层上已
弹好的方格网交点处安放支座和横梁,并应转动支座螺杆,先用小线和水平尺调整支座面高度至全室等高,待所有支座柱和横梁构一体后,应用水平仪抄平。
支座与基层面之间应连接牢固,可根据设计要求
用环氧树脂、膨胀螺栓或射钉连接。
6.4铺设活动地板
6.4.1根据房间平面尺寸和设备等情况,应按活动地板模数选择板块的铺设方向。
当平面尺寸符合活动地板板块模数,而室内无控制柜设备时,宜由里向外铺设,当平面尺寸不符合活动地板板块模数时,宜
由外向里铺设。
当室内有控制柜设备且需要预留洞口时,铺设方向和先后顺序应综合考虑选定。
6.4.2铺设前,活动地板面层下铺设的电缆、管线已经过检查验收,并办完隐检手续。
6.4.3先在横梁上铺设缓冲胶条,并用乳胶液与横梁黏合。
铺设活动地板块时,应调整水平度,保证四角接触处平整、严密,不得采用加垫的方法。
6.4.4铺设活动地板板块不符合模数时,不足部分可根据实际尺寸将板面切割后镶补,但不得小于整块
的1/3,并配装相应的可调支撑和横梁。
切割的边应采用清漆或环氧树脂胶加滑石粉按比例调成腻子封边,
或用防潮腻子封边,也可采用铝型材镶嵌。
6.4.5在与墙边的接缝处,应根据接缝宽窄分别采用活动地板或木条刷高强胶镶嵌,窄缝宜用泡沫塑料镶嵌。
随后立即检查调整板块水平度及缝隙。
6.5清擦和打蜡
当活动地板面层全部完成,经检查平整度及缝隙均符合质量要求后,即可进行清擦。
当局部沾污时,
可用清洁剂或皂水用布擦净晾干后,用棉丝抹蜡,满擦一遍,然后将门封闭。
如果还有其他专业工序操作时,做好成品保护。
待其全部工序完成后,再清擦打蜡交活。
7质量控制措施及检验标准
7.1质量控制措施
7.1.1作业环境:
在施工过程中应注意对已经完成的隐蔽工程管线和机电设备的保护,各工种间搭接应合理,同时注意施工环境,不得在扬尘、湿度大等不利条件下作业。
7.1.2平整度的保证
1)基层的平整度必须符合要求。
2)支座和横梁的架设是保证平整度最关键的步骤,应严格按照工艺标准操作。
做每个横梁都要控制标高,整体完成后还要再次整体抄平。
7.1.3施工过程控制
1)活动地板及其配套支承系列的材质和技术性能要符合设计要求,并有出厂合格证,大面积施工
操作前,要进行试铺工作。
2)弹完方格网实线后,要及时插入铺设活动地板下的电缆管线的工序,并经验收合格后再安支承系统,保证支架不被碰撞造成松动。
3)安装底座时,要检查是否对准方格网中心交点,待横梁全部安装完后要拉横竖线,检查横梁的平直度,以保证面板安装后缝格的平直度控制在3mm之内,面板安装之后随时拉小线再次进行
检查。
7.1.4成品保护
1)施工时应注意对定位定高的标准杆、尺、线的保护,不得触动、移位。
2)对所覆盖的隐蔽工程要有可靠保护措施。
3)活动地板面层完工后应进行遮盖和拦挡,避免受损坏。
4)后续工程在活动地板面层上施工时,必须进行遮盖、支垫,严禁直接在活动地板面上动火、焊接、和灰、调漆、支铁梯、搭脚手架等。
7.2质量控制表
表7-1质量控制表
序号
控制点
控制方式
W
H
S
1
定位放线
●
7.3质量检验标准
按照《10kV~500kV输变电及配电工程质量验收与评定标准第3部分:
变电土建工程》中的Q/CSG
表3-3.0.18-2、Q/CSG表3-5.2.1、Q/CSG表3-5.12.23、Q/CSG表3-BJ2-1、Q/CSG表3-BJ2-9规定执行。
附件1安全施工作业票
编码:
BDTJ-ZW-12~19-01/01
工作时间
工作地点
技术员
现场安全员
现场负责人
安全风险分析及控制措施
序号
危害名称
风险种类
风险等级
风险控制措施
1
梯子未装防滑措施
坠落
□可接受的风险
现场作业应严格执行相关安全规程及安全技术措施,并重点关注但不限于以下措施:
□装饰工程所用的砂浆、石灰膏、玻璃、涂料等,应集中加工和配置。
□严禁站在窗台上粉刷窗口四周线角。
□高处粉刷作业,必须搭设正规脚手架,作业人员必须正确系安全带;不得在易损建筑物或设备上搁置脚手架;不得将梯子搁在楼梯或斜坡上工作。
□抹灰使用的木凳、金属支架必须搭设稳固,经检查后方可使用。
□抹灰脚手架的跨度不得大于2m,架上堆放的材料不得过于集中,在同一跨度内不得超过2人。
□进行仰面粉刷时,应采取防止粉末等侵入眼内的防护措施。
□机械喷浆、喷涂时,操作人员应佩戴防护用品;梳浆应严格按照规定的压力进行,发生超压或管道堵塞时,应在停机泄压后进行检修。
□进行磨石工程时,应防止草酸中毒;使用磨石机应戴绝缘手套,穿胶鞋。
□在调制胶泥和铺设耐酸瓷砖时,室内应通风良好,工作人员应戴耐酸手套。
□上下作业用梯子必须牢固稳靠,不打滑。
□切割机等电动机具外壳必须接地,电源线绝缘良好。
□高处、临边及易脱落的材料和工器具必须设置牢固,有防坠落打击伤人的措施。
□有同一垂直面内上下交叉作业,应有隔离措施。
□脚手架的材料应分开堆放,不得超负荷堆放。
□洞口必须进行围设并覆盖,设置警示标示
2
梯子危险使用
坠落
□可接受的风险
3
离墙间距大且未设置封条板
打击
□可接受的风险
4
违规高处作业
坠落
□低风险
5
集中堆放的物料
坠落
□可接受的风险
6
同一跨度内超过两人同时作业
坠落
□可接受的风险
7
没有防护用品的作业
中毒、感染
□可接受的风险
8
漏电的设备
触电
□低风险
9
脱落的物体
打击
□可接受的风险
10
未佩戴防护用品
打击
□可接受的风险
11
防护不严的洞口
坠落
□可接受的风险
12
不稳固的索具作业
打击
□可接受的风险
13
坠落的砌体工具
打击
□可接受的风险
14
无安全措施的交叉作业
打击
□可接受的风险
15
用手牵吊绳
打击
□可接受的风险
16
材料放置在不稳妥的地方
打击
□可接受的风险
17
发生坠落的材料
打击
□可接受的风险
18
混乱的作业场所
打击、坠落
□可接受的风险
安全补充事项/平面布置图
现场接受交底人员签名
备注
说明:
(一)本票由现场技术员填写,现场安全员审核,现场负责人签发生效。
现场负责人开工前核对风险控制措施
并宣读。
(二)工作内容、地点、安全措施不变时本票最长可使用十天,否则应重新办票,用后上交备查;当人员发生变
更时,应在备注栏记录变更情况。
对新增人员进行交底,并签名确认。
(三)应根据现场条件、范围和环境,补充安全事项或平面布置图。
(四)当风险等级与基准风险等级不一致时,项目部应组织相关人员重新进行风险评估并制定措施。
(五)基准风险等级与风险控制措施在开工前现场打“√”。
(六)签名不齐全(含代签名的)均作废票处理。