系统集成项目管理工程师真题集锦英语题及答案剖析
系统集成项目管理工程师考试试题
•WliichoftliefollowingstatementrelatedtoPMOisnotcorrect?
(71)
(71)A.Thespecificform,function,andstructureofaPMOisdependentupontheneedsoftlieorganizationthatitsupports・
B.OneofthekeyfeaturesofaPMOismanagingsharedresourcesacrossallprojectsadministeredbythePMO.
C・ThePMOfocusesonthespecifiedprojectobjectives・
D・ThePMOoptimizestheuseofsiiaredorganizationalresourcesacrossallprojects・
[答案C]
•Theinputsofdevelopingprojectmanagementplandonotinclude(72).
(72)A.projectcharterB.stakeholdermanagementstrategy
C・projectscopestatementD.outputsfromplanningprocesses
[答案E]
•Aprojectlifecycleisacollectionofgenerallysequentialproject(73)whosenameandnumberaredeterminedbythecontrolneedsoftheorganizationororganizationsinvolvedintheproject.Tilelifecycleprovidesthebasic(74)formanagingtheproject,regardlessoftliespecificworkinvolved.
(73)A.phasesB.processesC・segmentsD.pieces
(74)A.planB.fractionC・mainD.framework
[答案A、D]
•(75)isoneofthequalityplanningoutputs.
(75)A.Scopebaseline
B・Costofquality
C・Productspecification
D・Qualitychecklist
[答案D]
系统集成项目管理工程师考试试题
69・71.Riskmanagementallowstheprojectmenagetandtheprojectteamnotto
(71)o(1.03分)
A.eliminatemostrisksduringtheplanningpiiaseoftlieproject
B.identifyprojectrisks
C.identifyimpactsofvariousrisks
D.plansuitableresponses
•标准答案:
A
70.72・Tlieprojectlife-cyclecanbedescribedas(72)。
(1.03分)
A.projectplanning,workauthorization,andprojectreporting
B.projectplanning,workautliorization,andpD[«Jectreporting
C.projectplanning,projectcontrol,projectdefinition,WBSdevelopment,andProjecttermination
D.projectconcept,projectexecution.Andprojectreporting
•标准答案:
A
71・73・(73)iSamethodusedinCriticalPathMetliodologyforconstructingaprojectschedulenetworkdiagramthatUSeSboxesOrrectangles,referredtOaSnodes,tOrepresentactivitiesandconnectstliemwitharrowsthatshowthelogicalrelationshipsthatexistbetweentliem・(1.03分)
A.PERTB.AOAC.WBSD.PDM
•标准答案:
D
72・74・ScheduledevelopmentcanrequirethereviewandrevisionOfdurationestimatesandresourceestimatestocreateanapproved(74)thatcanserveaSabaselinetotrackprogress・(1.03分)
A.scopestatementB.Activitylist
C.projectcharterD・projectschedule
•标准答案:
D
73.75・TheDevelopProjectManagementPlanProcessincludestheactionsnecessarytodefine,prepare,integrate,andcoordinateallconsfimentplansintoa(75)(1.03
分)
A.projectScopeStatement
B.projectManagementPlan
C.Forecasts
D.projectCharter
•标准答案:
B
系统集成项目管理工程师考试试题
试题(71)
Project(71)isanuncertaineventorconditionthat,ifitoccurs,liasapositiveoranegativeeffectonatleastoneprojectobjective,suchastime,cost,scope,orquality.
(71)A・riskB・problemC.resultD・data
试题(71)分析
风险是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影晌。
选项A是风险,选项B是问题,选项C是结果,选项D是数据。
根据项目风险定义,风险包括两方面含义:
一是未实现目标;二是不确定性。
因此应选择A。
参考答案
(71)A
试题(72)
Categoriesofriskresponseare(72)・
(72)A・Identification,quantification,responsedevelopment,andresponsecontrol
B・Marketing,technical,financial,andhuman
C・Avoidance,retention,control,anddeflection
D・Avoidance,mitigation,acceptance,andtransferring
试题(72)分析
应对风险就是采取什么样的措施和办法,跟踪和控制风险。
具体应对风险的基本措施一般为规避、减轻、接受、转移。
选项A是识别、量化、措施制定、措施控制,选项B是市场、技术、资金、人员,选项C是规避、保留、控制、偏离,选项D是规避、减轻、接受、转移。
因此应选择Do
参考答案
(72)D
试题(73)
(73)istheapplicationofplanned,systematicqualityactivHiestoensurethattheprojectwillemployallprocessesneededtomeetrequirements・
(73)A・Qualityassurance(QA)B・Qualityplanning
C・Qualitycontrol(QC)D・Qualitycosts
试题(73)分析
质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。
质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。
质量成本是指为满足质量要求所付出的主要成本。
质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。
选项A是质量保证(QA),选项B是质量计划,选项C是质量控制(QC),选项D是质量成本。
因此应选择A。
参考答案
(73)A
试题(74)
(74)isprimarilyconcernedwithdefiningandcontrollingwhatisandisnotincludedintileproject.
(74)A.ProjectTimeManagement
B.ProjectCostManagement
C.ProjectScopemanagement
D.ProjectCommunicationsManagement
试题(74)分析
项目范围管理是项目管理(包括时间、成本、沟通)的基础。
项目范围管理是最先定义和决定项目中包含哪些内容和确定边界的。
选项A是项目时间管理,选项B是项目成本管理,选项C是项目范围管理,逸项D
是项目沟通管理,因此应选择C。
参考答案
(74)C
试题(75)
Aprojectmanagerbelievestliatmodifyingthescopeoftheprojectmayprovideaddedvalueserviceforthecustomer.Theprojectmanagershould(75).
(75)A・assignchangetaskstoprojectmembers
B・callameetingoftheconfigurationcontrolboard
C・changethescopebaseline
D・postponetliemodificationuntilaseparateenliancementprojectisfundedafterthisprojectiscompletedaccordingtotheoriginalbaseline
试题(75)分析项目经理认为调整项目范围可以给客户提供増值的服务,项目经理应该怎么做。
选项A是安排任务变更到项目成员,选项B是召集变更控制委员会矣议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目矣得到客户的相应资金前,暂缓修改。
由于是在原内容基础上増加增值服务内容,超出原先范围,应先确定客户认可和増加新资金,因此应选择D。
参考答案
(75)D
系统集成项目管理工程师考试试题
•OSIisatheoreticalmodeltliatshowshowanytwodifferentsystemscancommunicatewitheachother・Router,asanetworkingdevice,operateatthe(71)layeroftheOSImodel・
该題的选项是Co
•MostofthehostoperatingsystemprovidesawayforasystemadministratortomanuallyconfiguretheIPinformationneededbyahost・Automatedconfigurationmethods,suchas(72),arerequiredtosolvetheproblem・
(72)A・IPsecB・DHCPC・PPTPD・SOAP
该題的选项是Bo
•Businessintelligence(BI)istlieintegratedapplicationofdatawareliouse,dataminingand(73).
诙題的选项是Ao
•PerformQualityControlistheprocessofmon让oringandrecordingresultsofexecutingtlieQualityPlanactivitiestoassessperformanceandrecommendnecessarychanges・(74)arethetecliniquesandtoolsinperformingqualitycontrol.
该题的选项是CO
①③©⑥是没有问题的,②Runchart是在PMBOK2003英文版里才见到,汗
•PlanQualityistheprocessofidentifyingqualityrequirementsandstandardsfortlieprojectandproduct,anddocumentingliowtlieprojectwilldemonstratecompliance・(75)isamethodthatanalyzeallthecostsincurredoverthelifeof
theproductbyinvestmentinpreventingnonconformancetorequirements,appraisingtheproductorserviceforconformancetorequirement,andfailingtomeetrequirements・
(75)A.Cost-BenefitanalysisB・Controlcharts
C・QualityfunctiondeploymentD.Costofqualityanalysis
该題的选项是Do
系统集成项目管理工程师考试试题
•TCP/IPcommunicationprotocolcontainsfourlayers・Frombottomtotop,tliefourlayersare_(71)_・
(71)
A・networkinterfacelayer,internetlayer,transportlayerandapplicationlayerB・internetlayer,networkinterfacelayer,transportlayerandapplicationlayerC・networkinterfacelayer,transportlayer,networkinterfacelayeranclapplicationlayer
D・applicationlayer,transportlayer,internetlayerandnetworkinterfacelayer【正确答案】:
A
•Ethernetisthecommonlyusedlocalareanetworkcommunicationprotocol.TliestandardofEthernetis_(72)_・
(72)A・IEEE802.1B・IEEE802.2C・IEEE802.3D・IEEE802.11【正确答案】:
C
•_(73)_arethefourmajoractivitiesofsoftwareconfigurationmanagement.
①configurationidentification②statementreport③changecontrol
④preparationofrequirementdocument⑤configurationauditing
(73)A.①②®®B.①②④⑤C.③⑤D.④⑤
【正确答案】:
C
•Theearnedvaluetechniqueisacommonlyusedmethodofperformancemeasurement・Itintegratesprojectscope,cost,andschedulemeasurestohelptheprojectmanagementteamassessprojectperformance.Ifaproject'sScliedulePerformanceIndex(SPI=EV/PV)valuelessthan1.0,itmeansthat_(74)_・
(74)
A・theprojectisalieadof让splannedschedule
B・lessworkwascompletedthanwasplanned
C・thecostoverrunforworkcompleted
D・thecostunder-runofperformancetodate
【正确答案】:
B
•SWOTanalysisisakindofriskidentificationmethod.IftlieprojectteamchosetheSOstrategy,theyshould_(75)_・
(75)
A・makefulluseoftheadvantageandcatchtheopportunity
B・overcomethewealmessandcatchtheopportunity
C・makefulluseoftheadvantageandreducethetlireat
D・overcometheweaknessandreducethethreat
【正确答案】:
A_
系统集成项目管理工程师考试试题
第71
题STheprojectmanagermustmaintainaneffectivecommunicationlinkw让hthecustomer'ssatisfactionwitlitheprogressoftheproject.Theprojectmanagermaintainstliislinkthrough(71).
(71)
A.periodicprojectreports,periodicvisitstothecustomer,andtelephonicexclianges
B.subordinates,projectteammembers,andtheprojectsponsor
C.one-timereports,weeklyreports,andmonthlyreports
D.thetelephone,facsimile,anddatatransmission
【正确答案】:
A
第72
题・Aprojectmanageriscalledtoaninformalmeetingw让hthecustomerandaproblemisraised・Thisproblemhasmajorimplicationsfortheprojectmanager*scompany,butthecustomerwantstopursueasolutionatthemeeting.Theprojectmanagersliould(72)・
(72)
A.tellthecustomerthathewillnotaddressanyproblemsbecausethisisonlyaninformationexchangemeeting
B.tellthecustomerthattheproblemisnotsufficientlydefinedtodeterminetheappropriateaction
C.collectasmuchinformationontheproblemwithoutcommittinghiscompanytoasolution
D.givethecustomerarangeofsolutionsthatmightbeacceptabletoliisCompany
【正确答案】:
c
第73
题•Theprojectscheduleismoretlianadocumentthatlaysouttheactivitiesovertimetorepresentthetimedimensionoftheproject,itisamanagementtooltobeusedfordecisionmaking.Assuch,thescheduleisusedbytlieprojectmanagementteamto(73)・
(73)
A.measure,delay,record,distribute,analyze,anddirect
B.plan,schedule,monitor,control,report,andforecast
C.promote,highlight,monitor,control,forecast,