美国项目管理PMP435道全英文试题Word文档格式.doc
《美国项目管理PMP435道全英文试题Word文档格式.doc》由会员分享,可在线阅读,更多相关《美国项目管理PMP435道全英文试题Word文档格式.doc(86页珍藏版)》请在冰点文库上搜索。
C.Acquisition,operations,maintenance.
D.Production,operations,maintenance.
E.Noneoftheabove
B
4.ManagementByObjectivesassumesthattheteam:
A.isreceptivetoanunstructuredenvironment.
B.doesnotrequireclosesupervision.
C.possessesaselfdirectedphilosophy
D.identifieswithprojectobjectives.
E.Alloftheabove.
5.Qualitymaybedefinedas:
A.conformancetorequirements.
B.fitnessforuse.
C.continuousimprovementofproductsandservices
D.appealtothecustomer
E.AlloftheaboveexceptB
6.Sinceriskisassociatedwithmostprojects,thebestcourseofactionisto:
A.coverallprojectrisksbybuyingappropriateinsurance
B.ignoretherisks,sincenothingcanbedoneaboutthemandmoveforwardwiththeprojectinanexpeditiousmanner.
C.avoidprojectswithclearandpresentrisks
D.eliminateallknownriskspriortotheexecutionphaseoftheproject
E.identifyvariousrisksandimplementactionstomitigatetheirpotentialimpact
7.Theprocessofchoosing/documentingthebestapproachtoachievetheprojectobjectivesispartof:
A.Thescopebaseline.
B.Scopeauthorization
C.Scopedefinition
D.Scopeplanning.
D
8.Timemanagementistheallocationoftimeinaproject'
slifecyclethroughtheprocessof:
A.Planning
B.Estimating.
C.Scheduling.
D.Controlling
9.Acomprehensivedefinitionofscopemanagementwouldbe:
A.Managingaprojectintermsofitsobjectivethroughtheconcept,development,implementation,andterminationphasesofaproject.
B.Approvalofthescopebaseline.
C.Approvalofthedetailedprojectcharter.
D.Configurationcontrol.
E.Approveddetailedplanningincludingbudgets,resourceallocation,linearresponsibilitychartsandmanagementsponsorship.
A
10.CostPlusPercentageofCostcontractsaremoredesirableforthe:
11.Managementstylesassociatedwithproductionenvironments,suchasassemblylinescommonlyinclude:
A.adirectingstyleofleadership.
B.alackofconfidenceintheirworkers
C.assumptionthatworkerslackambitionanddislikeresponsibility
D.aTheoryXstyleofleadership
12.Qualitymanagement:
A.isanothernameforcarefulinspections.
B.isinverselyrelatedtoproductivity.
C.isprimarilytheresponsiblityofmanagement.
D.isprimarilytheresponsibilityoftheworkers.
E.isessentiallyamotivationaltechnique.
C
13.Riskmanagementallowstheprojectmanagerandtheprojectteamto:
A.eliminatemostrisksduringtheplanningphaseoftheproject
B.identifyprojectrisks
C.identifyimpactsofvariousrisks
D.plansuitableresponses
E.B,CandDonly
14.Schedulingistheprocessbywhichdecisionsaremadeconcerning:
A.Taskstobeaccomplished.
B.Personnel/organizationthatwillbeassignedtoaccomplishthetask.
C.Timewhenthetasksaretobecompleted.
D.Alloftheabove.
E.AandConly.
15.Thebasicelementsofcommunicationinclude:
A.Listening,talkingandsignlanguage.
B.Communicator,encoding,message,medium,decoding,receiver,andfeedback
C.Clarityofspeechandgoodlisteninghabits
D.Reading,writingandlistening
16.Whichofthefollowingwouldmostlikelyincreasetheaccuracyofestimatingtheprojectcost?
A.Pricingouttheworkatlowerlevelsintheworkbreakdownstructure.
B.Usinghistoricaldata.
C.Talkingtopeoplewhohaveworkedonsimilarprojects.
E.AandConly.ANS:
17.Avarianceenvelopehasbeenestablishedonaproject.Theenvelopegoesfrom+-30%inR&
Dto+-5%duringmanufacturing.Thereasonforthechangeinthicknessoftheenvelopeisbecause:
A.Themanagementreservehasbeenusedup.
B.TheaccuracyoftheestimatesinmanufacturingareworsethantheestimatesinR&
D.
C.Tightercontrolsarealwaysneededasaprojectbeginstowinddown.
D.Ofthepersonaldesiresoftheprojectsponsor.
E.Ofnoneoftheabove
18.Costofqualityis:
A.associatedwithnon-conformancetospecificationsandrequirements.
B.primarilycausedbypoorworkmanshipofworkerswhoarebuildingormanufacturingtheproduct.
C.usedtodeterminewhetheraqualitymanagementprogramissuitableforagivenproject.
D.negligibleformostlargeprojects.
E.AandB
19.Managementplansincludeallofthefollowingexcept:
A.Organizationofproject.
B.Jobdescriptions.
C.Policiesandprocedures.
D.Linearresponsibilitycharts.
E.Scopebaseline.
20.TheJapaneseresourcemanagementmodelexhibits:
A.acooperativespiritofgoalsetting.
B.non-specializedcareerpaths
C.frequentchangesinteamassignments
D.aTheoryZstyleofmanagement
21.Thehighestdegreesofprojectriskanduncertaintyareassociatedwiththefollowingphaseoftheproject:
A.conceptual
B.execution
C.cut-over
D.postprojectevaluation
E.AandDonly
22.ThemostcommontypesofschedulesareGanttcharts,milestonecharts,lineofbalance,and:
A.Networks.
B.Timephasedevents.
C.Calendarintegratedactivities.
D.AandConly.
E.BandConly.
23.Whichofthefollowingisoftenoverlookedinachievingeffectivecommunication?
A.speakingclearly
B.listening
C.interpreting
D.maintainingeyecontact
E.manipulatingtheconversation
24.Whichtypeofcontractrequiresthatthebuyerkeepthetightestlabor/materialcostcontrol?
A.CostPlusIncentiveFee
B.CostPlusPercentageofCosts
C.CostPlusFixedFee
D.FirmFixedPrice
E.FirmFixedPricePlusIncentive
25.Atask-orientedfamilytreeofactivitiesisa:
A.Detailedplan.
B.Linearresponsibilitychart.
C.Workbreakdownstructure.
D.Costaccountcodingsystem.
E.Workpackagedescription.
26.Adding5peopletoa4personteamincreasesthecommunicationchannelsbyafactorof:
A.2times
B.3times
C.4times
D.5times
E.6times
27.Costmanagementincludes:
A.Costestimating/forecasting.
B.Costbudgeting/costcontrol.
C.Costapplications.
E.AandBonly.ANS:
28.ParticipativeManagement:
A.involvesthesolicitationofinformationfromallteammembers.
B.assumesthatmembersavoidworkandresponsibility.
C.suggeststhesharingofpoweranddecisionmaking.
D.employsaTheoryXstyleofleadership.
E.AandC
29.Theauditingfunctionthatprovidesfeedbackaboutthequalityofoutputisreferredtoas:
A.qualitycontrol.
B.qualityplanning.
C.qualityassurance.
D.qualityimprovement
30.Thelowestdollaramount'
atstake'
isassociatedwiththefollowingphaseoftheproject:
31.Themajordisadvantageofabarchartis:
A.Lackoftime-phasing.
B.Cannotberelatedtocalendardates.
C.doesnotshowactivityinterrelationships.
D.Cannotberelatedtomanpowerplanning.
E.Cannotberelatedtocostestimates.
32.Whichcontracttypeconsistsof-targetcosts&
profit,ceilingpricesandsharedratioofrisk?
33.Methodsandtechniquesusedtoexaminecostandtechnicaldataarecalledfeasibilitystudies.Theeconomicaspectsofafeasibilitystudy
includeinterestrates,presentworthfactors,operatingcosts,depreciationand_____.
A.Capitalizationcosts.
B.Technicalskillrequirements.
C.Technologyforecasting.
D.Strategicmarketingintelligence.
34.Standardofpurchasedmaterial:
A.Simplifiesinventorycontrol
B.reducestheriskofobsolescence
C.reducescostofpurchasingandstorage
35.The’controlpoints"
intheworkbreakdownstructureusedforisolatedassignmentstoworkcentersarereferredtoas:
A.Workpackages.
B.Subtasks.
C.Tasks.
D.Codeofaccounts.
E.Integrationpoints.
36.Theutilityofnetwork-basedschedules:
A.Revealsinterdependencies.
B.Facilitates"
whatif"
exercises.
C.Highlightscriticalactivities.
D.Providesinformationonresourcerequirements,timerequirementsandtradeoffs.
37.Thewayaprojectmanagersendsandreceivesinformationdependsupon:
A.Howothersrelatetotheprojectmanager
B.Theprojectmanager'
slevelintheorganizationalhierarchy
C.thesizeandnatureoftheproject
D.theprojectmanager'
ssalaryandage
E.thenumberofprojectsgoingonatonetimeinthecompany
38.Uncertaintyreferstoasituationwhere:
A.theoutcomesareknownbuttheirprobabilitiesarehigh
B.theoutcomesandtheirprobabilitiesa