COMPANYPROCEDURE
CP231.003/5Z
COSTCONTROL
REVISION
DATE
REVISIONDETAILS
0
29July1986
InitialIssue
1
02February1987
Rev.1(TotallyRevised)
2
27February1988
(a)RevisedHeaderformataspage1
(b)Added"CommercialLimitation"assection5.3.1andrenumberedexisting5.3.1to5.3.2
3
23May1990
(a)Totalrevision
(b)SplitEstimateDeviation(EDN)ProceduretoseparateProcedureCP231.007Z
4
14July1998
(a)ChangedCompanynametoKvaernerProcess(Netherlands)B.V.
(b)Generalrevision
5
11November2003
(a)ChangedCompanynametoAkerKvaernerNetherlandsB.V.
(b)AddedreferencestoCP231.009–RiskManagementandM0039–ContingencyRundownPlanning
Preparedby:
CostEngineeringDepartment
Approvedby:
ManagerCostEngineeringDepartment
Approvedby:
ManagerQuality&SafetyAssurance
Approvedby:
DirectorFinance&Control
Authorisedby:
ManagingDirector
TABLEOFCONTENTS
1.0SCOPEOFAPPLICATION5
2.0OBJECTIVES5
3.0DEFINITIONS5
3.1ControlEstimate5
3.2OriginalBudget5
3.3EstimateDeviation5
3.4CurrentBudget5
3.5Commitments6
3.6EstimatetoComplete6
3.7CurrentForecast6
3.8Expenditures6
3.9Trend6
3.10CodeofAccounts6
3.11DirectCosts6
3.12IndirectCosts6
3.13Escalation6
3.14Contingency7
4.0RESPONSIBILITIES7
4.1ProjectManager7
4.2CostEngineer7
4.3DisciplineLeadEngineers9
4.4PlanningEngineer9
4.5ConstructionManager9
4.6SubcontractEngineer9
4.7ProjectPersonnel10
5.0GENERALELEMENTS10
5.1BasisofControl10
5.2Budgets11
5.3Commitments11
5.4EstimatetoComplete12
5.5TrendMeeting12
5.6CurrentForecasts12
5.7Expenditures13
5.8ExpenditureForecastingandCashFlow13
5.9Escalation14
5.10Contingency14
5.11SubcontractControl15
5.12Backcharges15
6.0COSTREPORTING16
6.1MonthlyCostReport16
6.2FinalCostReport16
7.0REFERENCES17
1.0
SCOPEOFAPPLICATION
Thisproceduresetsoutactivitiesandresponsibilitiesthroughoutaprojectforcontrolling,forecastingandreportingofprojectcosts.
ChangeadministrationduringprojectexecutioniscoveredinCP231.007Z-EstimateDeviationNotice(EDN)Procedure.
2.0OBJECTIVES
Theobjectivesofthisprocedureareasfollows:
Identifyresponsibilitiesforcontrolling,forecastingandreportingofcostsduringallstagesofprojectexecution.
Establishproceduresforcontrolling,forecastingandreportingofcostsduringallstagesofprojectexecution.
Establishformatsforreportingandapprovals.
3.0DEFINITIONS
3.1ControlEstimate
Anestimatewhichisbaseduponaclearlydefinedandapprovedprojectscopeofwork,includingAkerKvaernerscopeofservices,andacleardefinitionofdeliverables.ItisnormallypreparedbytheEstimatingGroup,withinputfromtherelevantengineeringdisciplines.AClientpreparedestimatewhichhasbeenreviewedandagreedwithAkerKvaernermayalsobeused.TheestimateisusedtoestablishtheOriginalProjectBudget.
Itisnormallypreparedwhenthescopeofworkisknowninallmajorengineeringdisciplinesandtheprocessequipmenthasbeendefined.Itispreparedeitherduringaproposalorduringtheearlystagesoftheproject.Timingisdependentonscopedefinitionandcontractualconditions.
ItissetupandmaintainedinaccordancewiththeAkerKvaernerE&CEuropeCodeofAccountsandcoversalldirectandindirectcosts,escalationandcontingencies.
3.2OriginalBudget
FollowingapprovalbybothClientandAkerKvaernerManagement,theControlEstimatebecomestheOriginalBudgetfortheproject.
3.3EstimateDeviation
AnyconditionthatmayresultinavariancefromtheControlEstimate,eitherincostorschedule.
Duringprojectlife,changeswilloccurinworkscopeorprojectexecutionplanthatmaynecessitatebudgettransfers,additionsordeletionstotheoriginalbudgetand/orschedule.
3.4CurrentBudget
TheCurrentBudgetisbasedontheOriginalBudgetasdescribedinparagraph3.2above.
Itisregularlyupdatedduringprojectexecutiontoincorporateapprovedbudgettransfersandscopeadditions/deletionsresultingfromapprovedEDN's.TheupdatedCurrentBudgetisissuedinthemonthlyCostReport.
3.5Commitments
Thesearemadeduringprojectexecutionbyexpenditureofmanhoursandincidentals
andexecutionofcommercialagreements(eg.Letter’sofIntent,PurchaseOrders,ContractsandSubcontracts)whichwillresultinexpenditure.Assessmentofcommitmentvalueswilldependonthetypeofcontractualagreements,asdetailedinparagraph5.3.Commitments,andshallexcludeBTW/VAT.
3.6EstimatetoComplete
ThemostrecentforecastofCommitmentsstilltobemadetocompletetheproject.
ForamoredetailedexplanationofEstimatetoCompleterefertoparagraph5.4ofthisprocedure.
3.7CurrentForecast
ThetotalanticipatedcostoftheprojectresultingfromtheadditionofEstimatetoCompleteandcurrentCommitments.
ForamoredetailedexplanationofCurrentForecastrefertoparagraph5.6ofthisprocedure.
3.8Expenditures
Thetotalvalueofinvoicespaid(excl.BTW/VAT).
ForamoredetailedexplanationofExpendituresrefertoparagraph5.7ofthisprocedure.
InvoiceApprovalsaretheresponsibilityoftheAccountingDepartment.
3.9Trend
AnearlyidentificationofadeviationfromapartoftheCurrentBudgetthatmayresultinanoverrun/underruninoneormorecostareas.
3.10CodeofAccounts
AkerKvaernerE&CEuropeCodeofAccounts.
3.11DirectCosts
CostsofallitemsofequipmentandmaterialinstalledintheconstructionofthePlanttogetherwiththecostsoflabourandmaterialsusedininstallingthem,asspecifiedintheoriginalcontractscopeofwork,andasamendedviatheEDNprocedure.
3.12IndirectCosts
AllcostsincurredinachievingtheengineeringandconstructionofthePlant,butforitemswhicharenotdirectlyincorporatedinthePlant.TheseincludeEngineering,Procurement,ConstructionManagement,Incidentalcosts,etc.
3.13Escalation
Fundswhichareallocatedintheestimatetocompensateforchangesinpricesofmaterialandwageratesoccurringbetweenthetimetheestimateispreparedandthetimeofactualengineering,purchaseanddeliveryofequipment,materialsandconstruction.Estimatesarenormallypreparedonthebasisofcurrentpriceandwagerateswithanallowanceforfutureanticipatedescalation.
ForamoredetailedexplanationofEscalationrefertoparagraph5.9ofthisprocedure.
3.14Contingency
Fundswhichareallocatedintheestimateasspecificprovisionforunforeseeableelementsofcostwithinthedefinedprojectscopeofwork.
ForamoredetailedexplanationofContingencyrefertoparagraph5.10ofthisprocedure.
4.0RESPONSIBILITIES
4.1ProjectManager
ThemainresponsibilitiesoftheProjectManagerinCostControlare:
-concurrencetoamendmentsofthestandardCostControlProcedure,forapprovalbyAkerKvaernerManagement,tocoverClientrequirements,
-achievementofallcontractcostandbudgettargets,
-reportingprojectcoststatusmonthlytoClientandAkerKvaernerManagementinaccordancewiththisprocedure,
-schedulingandconductingmonthlycosttrendmeetings,
-reviewandapprovalofDesignChangeRequests(DCR's)inaccordancewithCompanyProcedureCP231.007Z,
-preparation,approvalandissuetoClientofOrderOfMagnitudechanges(OOM's)inaccordancewithCompanyProcedureCP231.007Z,
-identification,initiationandtimelypreparation,review,approvalandissuancetoClientofEDN'sinaccordancewithCompanyProcedureCP231.007Z.
4.2CostEngineer
ThemainresponsibilitiesoftheProjectCostEngineerare:
-familiarisehim/herselfwiththeContract,ProjectProcedures,ControlEstimateandscopeofworkusedasbasisfortheControlEstimate.
-amendthestandardCostControlProcedure,ifrequiredbytheClient,fortheconcurrenceoftheProjectManagerandapprovalbyAkerKvaernerManagement,thusestablishingtheagreedCostControlProcedurefortheproject,forinclusioninDesignDataNo.1,
-supporttheProjectManagerinthesuccessfulimplementationoftheCostControlProcedure,forEngineering,ProcurementandConstructionactivities,
-assistandadvisetheProjectManageroncostrelateditemstominimisetheprojectcost,
-Continuallymonitordesigndevelopmentagainsttheoriginalscope(Estimatebasis)toidentifychangesandcostimpacts.ChallengetheneedforchangestothedesignwhichcausecostincreaseswhichcannotberecoveredviatheEDNprocedure.
-preparetheOriginalBudgetbasedupontheapprovedControlEstimateafterreviewoftheControlEstimatewiththeEstimatingGroup,
-issuedisciplineman-hourbudgetstoDisciplineLeadEngineersafterco-ordinationwithandapprovaloftheProjectManager,
-obtaincopiesofvendorbidsuponreceiptbypurchasingandreviewagainsttheCurrentBudgetinordertoprovideanearlywarningsystem,whenbidsareoverthebudget,totheProjectManager,
-assignbudgetvaluestoEngineeringAnalysis/QuotationAnalysis(EA/QA's),analysevariancesbetweentheCurrentBudgetvalueandrecommendedQAvalue,priortoapprovalbytheProjectManager,
-obtaindataoncommitmentsandexpenditurestodateforengineering,incidentals,materials,constructionmanagementandsubcontractcostsandmaintainanup-to-datecommitment/expenditureregisteraspartofthecostreportdatabase,
-participateinmonthlyCostTrendMeetingstoreviewcostswiththeProjectManager,DisciplineLeadEngineersandProcurementRepresentativeinordertoevaluateandrev