装修工程施工方案
洁净室装饰装修施工方案
一、工程概况ScopeDescription
本系统为动物房室内装饰装修部分,主要包括可上人吊顶安装、洁净隔墙隔墙安装、门窗安装以及其他零星工程。
ThissystemisthedecoratingandrefurbishingpartofindoorAFbuildings.Theprojectsmainlyinclude:
Walk-onceilingfixing、cleanwallfixing、door、windowandotherprojects.
二、施工方案MethodStatement
1.二次吊挂系统Secondhangersystem
1.1施工准备Constructionpreparation
施工准备材料及主要机具materialsandmajorequipment:
二次吊元系统的材料:
定长9.6m60*80*2.5C型钢、40*40*3.2镀锌垫片(上吊点垫片)、60(长)*53(宽)*4.5镀锌垫片(下吊点垫片),69.5(宽)*60(长)*4.5(厚)镀锌C型卡箍(下吊点卡箍),69.5(宽)*150(长)*4.5(厚)镀锌C型卡箍(C型钢接头卡箍),与60×80C型梁配套的弹簧螺母(C型钢接头用),100*50*4方形调节器,M12全牙螺杆.
SecondaryhangingsystemMaterial:
length9.6m60*80*2.5Csteel,40*40*3.2galvanizedgasket(upperhangingpointgaskets),60(length)*53(W)*4.5galvanizedgasket(belowhangingpointunderthepads),69.5(W)*60(length)*4.5(thickness)galvanizedC-clamp(belownhangingpointclamp),69.5(W)*150(length)*4.5(thick)galvanizedC-clamp(C-shapedsteelconnectorclamp),and60×80C-beamssupportingspringnuts(C-shapedsteelconnector),100*50*4squareregulator,M12Threadedrod.
主要机具:
升降平台、墨斗(或粉线包)、小线、激光红外仪、笤帚、钢尺、红铅笔、油刷、榔头、螺丝扳手、冲击钻、焊机、套筒扳手。
Majorequipment:
liftplatform,fountain(orpinklinepackage),asmallwire,laserinfraredinstrument,broom,ruler,redpencil,oilbrush,hammer,wrench,impactdrill,weldingmachine,wrench.
1.2工艺流程Process:
放线支吊架加工吊杆安装C型钢安装
Setting-out
supportsandhangersprocessing
boominstallation
C-shapedsteelinstallation
Ø放线:
内装专业应严格按照二次深化设计的吊杆布局图纸进行定位放线;
Settingout:
Interiorprofessionalshouldbestrictlyinaccordancewiththedetaileddesignofthesecondaryboomlayoutdrawingstoposition.
Ø支吊架加工:
C型钢顶面标高为-3.200m,依据设计图纸制作吊杆;supportsandhangersprocessing:
C-shapedsteeltopelevationis-3.200m,fabricatetheboomaccordingtothedesigndrawing;
Ø吊杆安装:
本工程的吊杆应避开梁底位置,使用M12模扩底敲击式锚栓,有效锚固深度40mm;吊杆采用M12全牙螺杆。
Boominstallation:
Theboomofthisprojectshouldavoidthebttomofthebeam,usetheM12modeltheM12Zykonhammersetanchor,theeffectiveanchoragedepthis40mm;boomusethreadedrod;
节点:
锚栓安装节点
anchorinstallationnode
ØC型钢安装:
待主风管安装完毕之后,内装专业开始挂C型钢。
C型钢安装过程中,切口必须做防腐处理,安装完两头必须装堵头。
CsteelInstallation:
afterthemainductisinstalled,theinteriorfinishdisciplinestarteshangingCsteel.IntheprocessofCsteelinstallation,thecuttingmustbedonethecorrisiontreatment,aftertheinstallationiscompleted,plugmustbeinstalledatbothends.
C型钢及吊点布置平面图
C-shapedsteelandhangingpointlayourplan
C型钢安装节点
C型钢与C型钢的连接节点
C-shapedsteelandtheconnectingnodeofC-shapedsteel
2.吊顶工程Ceilingworks
2.1施工准备Constructionpreparation:
Ø熟悉设计图纸,明确技术要求;
Befamiliarwiththedesigndrawings,clearthetechnicalrequirements
Ø施工机具准备:
活动脚手架、人字梯、云石机、铝材切割机、临时用电配电箱、接线板、电焊机、曲线锯、吸尘器、手电钻、电锤、铆枪、卷尺、墨斗、画针、铁锤、吸盘、胶枪等。
Constructionequipmentpreparation:
movablescaffold,Ladders,marblemachine,aluminumcuttingmachine,temporarypowerdistributionboxes,wiringboard,weldingmachines,jigsaw,vacuumcleaners,handdrill,hammer,rivetgun,tapemeasure,fountain,drawingpins,hammers,chuck,gluegun;
Ø施工材料准备:
55mm厚双抗双面玻镁岩棉夹芯彩钢板顶板ConstructionMaterialpreparation:
55mmthickdouble-sidedanti-magnesiummineralwoolsandwichcolorsteeltopplate;
2.2operatingconditions:
作业条件:
Ø二次吊挂系统安装结束;
ØSecondaryhangingsysteminstallationiscomplete;
Ø施工用电电压正常;照明光线良好
Constructionpowervoltageisnormal;lightingisgood;
Ø吊顶内主风管、主水管、主桥架等安装结束;
Theinstallationofthemainduct,waterpipeandcabletrayintheceilingiscompleted.
2.3施工流程:
theconstructionprocess:
Ø测量尺寸:
将实际尺寸测量记录下来,现场与图纸的误差反映到图纸上,并根据实际误差调整施工方案;
Measurements:
Theactualsizemeasurementsarerecorded,theerrorsofsieanddrawingsarereflectedonthedrawing,themethodstatementisadjustedbasedontheactualerrors
Ø放线定位:
根据吊顶排板图进行放线定位;
Setting-outandpositioning:
carryoutthesetting-outandpositioningaccordingtoceilingplatearrangementdiagram
Ø龙骨安装:
根据吊顶排板图,安装吊顶板龙骨,龙骨型号:
LX2229;Keelinstallation:
installceilingpanelskeelaccordingtoceilingplatearrangementdiagram,keelModel:
LX2229;
Ø安装顶板:
每一块顶板严格按照二次设计排版图的编号进行安装,尤其是有风口、灯具孔预留洞的吊顶板。
顶板安装需及时加固,长短短边采用M6*25@400mm六角法兰自攻自钻螺丝加固,顶板四角采用M6*45的六角法兰自攻自钻螺丝固定;
Installtopplate:
Everytopplatedisinstalledinaccordancewiththenumberofsecondarydesignlayoutdiagram,especiallytheceilingwithdiffuser,reservedholeoflightingfixtures.Topplatemountingneedsthetimelyreinforcement,shortsideuseM6*25@400mmhexflangeselfdrillingscrewstoreinforcefourcornersoftopplateusesM6*45hexflangeselfdrillingscrews;
Ø板缝打密封胶;
Theplateseamisgluedwithsealant:
Ø彩钢板撕膜,打扫卫生。
Colorplatetearfilm,cleaning.
吊顶综合布置平面图
Ceilingcomprehensivelayouts
吊顶安装节点
(1)
ceilinginstallationnode
(1)
吊顶板安装节点
(2)
ceilinginstallationnode
(2)
吊顶与主体结构刚性连接节点
Ceilingandthewallconnectionnode
顶板预留口示意图
TopplatereservedopeningSchematic
2.4吊顶施工注意事项Constructionnoticeontheceiling
Ø吊顶临边维护Peripheralenclosureoftheceiling
Ø吊顶灯具、风口等预留洞须及时使用足够强度的木板封闭,并采取限位防移动措施;
Thereservedopeningsfortheceilingfixturesanddiffusersshallbepromptlysealedbywoodenplatewithenoughstrength,andthelimitanti-mobilemeasuresshouldbetaken.
Ø吊顶板保护CeilingProtection
Ø上吊顶施工作业需提出申请,由我方专业主管及安全主管审批才能进行作业;
Constructiononceilingneedtoapplybyourprofessionalmanagerandsecuritysupervisorapprovalforwork;
Ø吊顶安全承载能力150Kg/M2(附检测报告),严禁施工人员扎堆施工,保证一块板上站立不超过2人;严禁材料集中堆放,需保证在150kg/m2范围之内;
Thesafecarryingcapacityoftheceilingis150Kg/M2(attachedtestreport),itisprohibitedthattheconstructionworkersgettogethertowork,toensurethatthereisnotmorethantwopeopletostandontheboard;itisprohibitedthatthematerialsareconcentratedstacked,itisneededtobeinthescopeofthe150kg/m2;
Ø凡是所携带的施工工具必须放在工具包内,严禁随手携带丢扔工具;
Allthecarriedconstructiontoolsmustbeplacedinthetoolkit,itisstrictlyprohibitedtothrowthetoolsaway;
Ø施工区域需要动火作业的必须在下方铺设有效面积的防火布;
Constructionareaneedsthehotwork,thefireproofclothoftheeffectiveareamustbelaid;
Ø严禁在吊顶板上嬉戏打闹;严禁在顶板上大小便;
Itisprohibitedtoplayortoiletontheceilingroof;
Ø严禁在顶板上搭设脚手架施工;
Itisprohibitedtoerectthescaffoldingontheceilingforconstruction;
Ø在吊顶上施工必须做到有意识保护成品,如有损坏及时报告,做出维修,不能隐瞒,一经查出将严厉处罚;
Beawareofprotectingthefinishedproducts,whenworkingontheceiling,promptlyreportanydamageandmakerepairs,cannothide,onceidentified,theseverepunishmentwillbedone;
Ø在顶板上施工的垃圾必须及时清理,做到每日的垃圾每日清理;
Thegarbageontheceilingmustbepromptlycleanedup,thedailygarbageiscleanedeveryday;
Ø吊顶上有刷油漆或保温作业时,严禁将油漆及保温胶水洒落在顶板上,须在施工区域铺设彩条布保护。
Whenthereisthepaintorinsulationworkontheceiling,itisprohibitedtospillthepaintandinsulationglueontheroof.theconstructionareaisrequiredtolaythecolorfulstripedclothforprotection.
3.隔墙工程PartitionConstruction
1.施工准备ConstructionPreparation
Ø材料准备:
50mm厚岩棉夹芯板、100系列MAX隔墙、天地轨等;Materialpreparation:
50mmthickrockwoolsandwichplate,100SeriesMAXpartiotions,earthorbit,etc;
Ø主要工具准备:
活动脚手架、人字梯、冲击钻、铆钉枪、手电钻、水平尺、激光水平仪、型材切割机、磨光机等.
maintoolspreparation:
movablescaffolding,Ladders,impactdrill,rivetguns,handdrill,spiritlevel,laserlevel,profilecuttingmachine,grinder,etc.
2.作业条件operatingcondition
Ø隔墙排版图设计、审批完成;
ØPartitionlayoutdiagramdesignapprovaliscompleted;
Ø土建墙施工结束;顶板安装完成。
Civilwallconstructioniscompleted;
Topplateinstallationiscompleted.
3.施工工艺ConstructionProcess
地面清洁处理放线定位
天地轨安装
墙板安装
圆弧角、护墙板安装
清洁打胶
Groundorbitinstallation
wallpanelinstallation
Arcangle,wallguardsinstallation
cleaningandgluing
Ø地面清洁处理:
地表不得有过于明显的凹凸不平,可用铁锤或铁铲对地表面的水泥块,等杂物进行清理。
Groundcleaningtreatment:
surfacemaynothavetooobviousirregularities,cancleanupthecementblocks,andotherdebrisofonthegroundsurfacewithahammerorashovel.
Ø放线定位:
用墨线在地表划出隔间墙的中心线或边线位置,并对门窗进行定位。
Seting-outandpositioning:
Useinklinetodrawcenterlineoredgelineofpartitiononthesurface,andcarryoutthedoorandwindowpositioning.
Ø天地轨安装:
隔墙踢脚高度为100mm,在安装地轨的时候,需要使用激光水平仪对地轨高度进行定位,确保踢脚高度,地轨采用铆钉M5*30与地面固定,天轨采用M4*20自攻自钻螺丝与顶板连接。
Groundorbitinstallation:
partiotionskirtingheightis100mm,wheninstalltheearthorbit,youneedtousethelaserleveltopositionthrgroundrailheightandmakesuretheskirtingheight,railusestheM5*30rivetstobefixedwiththeground,SkyrorbitusesM4*20selfdrillingscrewstoconnectedwiththetopplate.
Ø墙板安装:
根据墙板排版图对墙板进行按序安装,尤其注意有管线预埋的墙板安装;
WallpanelInstallation:
carryoutthesequentialinstallationofthewallpanelaccordingtothewallpanellayoutdiagram,inparticular,playattentiontowallpanelinstallationwiththeembeddedpipeline;
Ø圆弧角、护墙板安装:
洁净室内阴角安装内圆,护墙板安装根据护墙板平面图布置;
Arcangle,wainscotinginstallation:
thenon-exposuredcornerinstalltheinnercircleinthecleanroom,wainscotinginstallationisaccordingtowainscotingplanlayout;
Ø清洁打胶:
对洁净室进行清洁,对板缝进行打胶。
Cleaningandgluing:
cleanupthecleanroom,gluetheplateseamwithsealant
墙板立面图
50mm墙板安装节点
(1)
50mmCleaningPlateInstallationNode
(1)
50mm厚隔墙节点
(2)
50mmCleaningPlateInstallationNode
(2)
转角节点图
100mm隔墙安装节点如下100mmCleaningPlateInstallationNode:
4.门窗工程Doorandwindow
1)门窗安装说明
Installationinstructionsofdoorandwindow
Ø本项目门窗安装主要为洁净室隔墙上的洁净密闭门、净化密闭观察窗以及防火门安装。
Doorsandwindowsfortheprojectmainlyrefertocleancloseddoorobservationwindowsandfiredoor.
Ø洁净门窗要求满足洁净室“密闭、净化、安全可靠”等技术性能。
Beinaccordancewithtechnicalperformancessuchasclosing,cleaning,safetyandreliabilityfordoorandwindowofcleanroom.
2)门安装流程
Installationprocessofcleandoor
3)密闭窗安装流程
Installationprocessofclosedwindow
4)门窗安装节点图
Installationnodediagramofdoorandwindow
不锈钢门套节点