PMPPreparationTrainingEndOfCourseExam
EndofCourseExam
1.WhichofthefollowingisnotaProjectManagementKnowledgeArea
A.CommunicationsManagement
B.ProcurementManagement
C.ChangeControlManagement
D.ProjectIntegrationManagement
E.ScopeManagement
2.Aprojectisa_____________effortundertakentocreatea_____________productorservice.
A.unique,temporary
B.significant,necessary
C.organized,profitable
D.temporary,unique
E.noneoftheabove
3.Possiblesocioeconomicinfluencesontheprojectinclude
A.Budgetaryconsiderations
B.Internationalization
C.Activitybasedcosting
D.Matrixorganization
E.Lifecyclemanagement
4.Basedonthelifecyclemodelofthetypicalproject,whichstageisexpectedtoexperiencethehighestresourceusage?
A.Initialphase(s)
B.Intermediatephase(s)
C.Closingphase(s)
D.PhaseIV
E.Staffingphase(s)
5.Whichisnotafacilitatingprocess?
A.Solicitationplanning
B.Procurementplanning
C.Qualityplanning
D.Communicationsplanning
E.Resourceplanning
6.Coreprocesses:
A.Caninteractdifferentlywithone-another,dependingonthenatureoftheproject
B.Havecleardependencies
C.Mustbepreformedsimultaneously
D.Aremanagedbythesamestaffmembersthroughouttheproject
E.Aredefinedasthoseprocessesinvolvedinmonitoring,measuring,andtakingcorrectiveaction
7.
Whichofthefollowingisatoolortechniqueusedinoverallchangecontrol
A.Organizationalprocedures
B.Performancereports
C.Projectplanupdates
D.Performancemeasurement
E.Alloftheabove
8.Theprojectplan:
A.Isamanagementcontrolthatwillchangeonlyintermittentlyandonlyinresponsetoanapprovedscopechange
B.Usuallyincludestheworkbreakdownstructurebutnotmajormilestones
C.Providesthebaselineagainstwhichchangeswillbecontrolled
D.Includesassumption,butnotconstraints
E.Alloftheabove
9.Changecontrolrequests:
A.Mustberelayedinwriting
B.Providethebaselineagainstwhichchangeswillbecontrolled
C.Arealwaysinitiatedexternally
D.Areinputstooverallchangecontrol
E.Areoutputsofoverallchangecontrol
10._________istheformalprocedureforapprovingprojectwork.
A.Work-authorizationsystem
B.Organizationalprocedures
C.Statusreview
D.Organizationalpolicies
E.Projectplanning
11.Whichofthefollowingisnotatoolortechniqueofprojectplanexecution?
A.PMInformationsystem
B.Work-authorizationsystem
C.Changecontrolsystem
D.Organizationalprocedures
E.Generalmanagementskills
12.Whichscopemanagementprocessprovidesabaseline?
A.Initiation
B.Scopeplanning
C.Scopedefinition
D.Scopeverification
E.Scopechangecontrol
13.ProjectScopeManagementis:
A.Usedtomakesurethatallworkrequired,andonlytheworkrequired,isincludedinordertocompletetheprojectsuccessfully
B.Thefeaturestobeincludedinaproductorservice
C.Issynonymouswithchangecontrolmanagement
D.Isconductedprimarilybyexternalstakeholders
E.Processesrequiredtoproperlycoordinatethevariouselementsoftheproject
14.Whichofthefollowingisnotanoutputoftheinitiationprocess
A.Projectcharter
B.Constraints
C.Alternativesidentification
D.AssignmentofthePM
E.Assumptions
15.ThelowestleveloftheWBSis:
A.Controlaccount
B.Codeofaccounts
C.Summaryleveltask
D.WorkPackage
E.Deliverable
16.Stakeholderacceptanceiscrucialtowhatphaseofthescopemanagementprocess
A.Initiation
B.Scopeplanning
C.Implementation
D.Scopeimprovement
E.Scopeverification
17.Anactivityhasaoptimisticdurationestimateof2days,amostlylikelyestimateof5days,andapessimisticestimateof8days.Whatistheweightedaverageduration?
A.4
B.5
C.5.2
D.5.5
E.6
18.Whichmethoddoesnotuseboxesornodestorepresentworkoractivities?
A.PERT
B.PDM
C.GERT
D.ADM
E.CDM
19.
Eachboxisanactivity;thenumberitcontainsisthedurationoftheactivityindays.Thedurationofthecriticalpathis:
A.16days
B.19days
C.14days
D.20days
E.22days
20.Amethodofshorteningthedurationoftheprojectis:
A.Lead
B.Creatingmilestones
C.Fasttracking
D.Leveling
E.EarnedValueManagement
21.Whichisatoolortechniqueofthescheduledevelopmentprocess?
A.Resourcepooldescription
B.Supportingdetail
C.Durationcompression
D.Activitydurationestimates
E.Analogousestimating
22.WhichtypeofestimateisbasedontheWBS?
A.Top-down
B.Parametric
C.Rolling
D.Bottom-up
E.Analogous
23.
Usingthechartbelow,whatisthebudgetvariance?
BCWS
BCWP
ACWP
$10,000
$12,000
$15,000
A.$2,000
B.$5,000
C.$3,000
D.–$2,000
E.–$3,000
24.Whichisnotapartofthecostbudgetingprocess?
A.Cost-estimatingtoolsandtechniques
B.Costestimates
C.Resourcerequirements
D.WBS
E.Projectschedule
25.Costestimatingis:
A.Assessinghowmuchtheorganizationwillchargefortheproductorservice
B.Assessinghowmuchitwillcosttheorganizationtoprovidetheproductorservice
C.Establishingabaselinetouseinmeasuringprojectperformance
D.Analyzingpositiveandnegativevariances
E.Noneoftheabove
26.EarnedValueis:
A.Theamountfuturevalueofapresentinvestment
B.Theactualhoursworkedontheprojectmultipliedbythebudgetedlaborrate
C.Acomponentoftheinitialfeasibilitystudy
D.BCWS–ACWP
E.Budgetedvalueofworkactuallyaccomplished
27.Thefuturevalueof$3000investedfor5yearsat12interestis:
A.$1,702.00
B.$4,702.00
C.$4,982.00
D.$5,287.00
E.$5,394.00
28.Whichofthefollowingisnotpartofthequalityassuranceprocess?
A.Operationaldefinitions
B.Qualitypolicy
C.Qualityaudits
D.Qualityimprovement
E.Qualitymanagementplan
29.
Apackingprocessresultsaproductwithameanweightof8ounces.Theprocesshasastandarddeviationof0.5ounce.Whatpercentageofsampleswillweighbetween7.5and8ounces?
A.23.87
B.31.74
C.34.13
D.68.26
E.95.46
30.WhatistheprimarymotivationaltoolofqualityTheoryX?
A.Zerodefectspromotionalcampaign
B.Useofthequalitycircle
C.Transferredresponsibility
D.Financialcompensation[Slide9-32]
E.Benchmarking
31.Whichofthefollowingispartofmodernqualitymanagement?
A.UsingZeroDefectsasamotivationtechnique
B.Considering95percentofqualitycoststheresponsibilityofmanagement
C.Addressingboththeprojectmanagementandtheproduct
D.Relyingonfrequentinspection
E.Tracing80percentofdefectscanbetracedbackto20percentoftheworkforce
32.Whichofthefollowingisnotaconsideredafailurecost?
A.Rework
B.Recall
C.Rejects
D.Scrap
E.Noneoftheabove
33.Apersonwhoisattemptingtofulfilltheneedforsafetyhasalreadysatisfiedwhichneeds?
A.Esteem
B.Self-Actualization
C.Physiological
D.Social
E.None
34.Whichofthefollowingisaninputtotheteamdevelopmentprocess?
A.Generalmanagementskills
B.Inputstoperformanceappraisals
C.Staffingpooldescription
D.Externalfeedback
E.Projectteamdirectory
35.Inaweakmatrixtheprojectmanager’sauthorityislikelytobe:
A.Non-existent
B.Low
C.Lowtomedium
D.Mediumtohigh
E.High
36.Whichtheoryspecifieshygienicconditionsasanimportantemployeemotivator?
A.TheoryX
B.TheoryY
C.McGregor’s
D.Hertzberg’s
E.Maslow’s
37.Dualreportingismostlikelytooccurinwhichtypeoforganization?
A.Functional
B.Projectized
C.Matrix
D.Laissez-faire
E.Noneoftheabove
38.Whichofthefollowingisnotapartoftheinformationdistributionprocess?
A.Workresults
B.Projectplan
C.Projectrecords
D.Communicationskills
E.Stakeholderanalysis
39.Whichistheprocessthatinvolvesgathering,generation,anddisseminatinginformationinordertoformalizetheacceptanceoftheproductbythesponsor,client,orcustomer?
A.Communicationsplanning
B.Informationdistribution
C.Scopeacceptance
D.Performancereporting
E.Administrativeclosure
40._________________specifiestowhominformationwillflowandwhatmethodwillbeusedtodistributevarioustypesofinformation.
A.Collectionandfilingstructure
B.Communicationsrequirements
C.Distributionstructure
D.Constraints
E.Noneoftheabove
41.WhichofthefollowingisnotoneoftheRiskManagementprocesses?
A.Riskidentification
B.Riskquantification
C.Riskassessment
D.Riskresponsedevelopment
E.Riskresponsecontrol
42.
Riskresponsedevelopmentisoneofthe_______________processes
A.planningcoreprocesses
B.planningfacilitatingprocesses
C.executingfacilitatingprocesses
D.controllingcoreprocesses
E.controllingfacilitatingprocesses
43.
Usingthefigurebelow,whatistheprobabilitythatthetaskwillbecompletedontimeandunderbudget?
A.12.5%
B.16.25%
C.25.0%
D.90.0%
E.Noneoftheabove
44.Usingacontractortoperformahighrisktaskiswhichformofriskresponse?
A.Insurance
B.Assumption
C.Alternative
D.Transference
E.Mediation
45.Thecontracttypethatrepresentsthelowestrisktothecustomeris:
A.CPIF
B.FPI
C.FFP
D.CPFF
E.CPPC
46.Thecontracttypethatrepresentsthegreatestrisktothecustomeris:
A.CPIF
B.FPI
C.FFP
D.CPFF
E.CPPC
47.
Whichisadocumentusedtosolicitproposalsfrompotentialbuyers?
A.IFB
B.RFP
C.RFQ
D.Invitationfornegotiation
E.Alloftheabove
48.WhichisnotaprocessofProcurementManagement?
A.Solicitationplanning
B.Solicitation
C.Solicitationselection
D.Contractadministration
E.Contractcloseout
49.Meetingwithprospectivesellerspriortopreparationofap