1.Whichofthefollowingisacharacteristicofprojectwork?
B
A.Projectshaveapermanentnature
B.Projectsrequirepeoplewithvariousanddifferentskills
C.Projectsrepeatthesameworkoverandover
D.Projectsremovealluncertaintyfromthework
2.Whichofthefollowingisacharacteristicofprojectwork?
D
A.Eachprojectisthesameasthepreviousone
B.Projectsdonotneedtoendatall
C.Everyprojectusesthesameteamofpeople
D.Projectsintroducechange
3.Whichofthefollowingisacharacteristicofprojectwork?
A
A.Projectsaretemporaryinnature
B.Projectscanonlybeundertakenwhentherearenoknownrisks
C.Everyprojectmusthavethesamesupplier
D.Projectsandbusinessasusuallyarethesamediscipline
4.Whichofthefollowingisacharacteristicofprojectwork?
C
A.Projectsremovealluncertaintyfromthework
B.Projectsarepermanentundertakings
C.Projectsintroducechange
D.Projectssolveeverybusinessproblem
5.Whichofthefollowingdoesprojectmanagementwishtocontrol?
B
A.People
B.Costs
C.Profit
D.Space
6.Whichofthefollowingdoesprojectmanagementwishtocontrol?
C
A.Timekeeping
B.Absenteeism
C.Benefits
D.The‘dayjob’
7.Whichofthefollowingdoesprojectmanagementwishtocontrol?
D
A.RiskandPeople
B.QualityandQuantity
C.WorkpracticesandScope
D.CostsandTimescales
8.Whichofthefollowingdoesprojectmanagementwishtocontrol?
C
A.Businessasusual
B.Theoriginalideafortheproduct
C.RiskandScope
D.Longtermproductuse
9.WhichofthefollowingistrueforPRINCE2?
C
A.Itcanonlybeusedoncertaintypesofproject
B.Itisspecifictocertainindustries
C.Itcanbeappliedtoanyproject
D.ItconcentratedontheSpecialisttechniquesusedbdevelopers
10.WhydoesPRINCE2suggestthatastudytoinvestigatethesituationanddetermineoptionsforthewayaheadberunasaseparateproject?
A
A.EachoptionwouldhaveadifferentProjectPlan,BusinessCaseandsetofrisks
B.Itwouldover-complicatetheproject
C.PRINCE2cannothandlemultipleoptions
D.Afeasibilitystudycannotbepartofaprogramme
11.WhichofthefollowingstatementsisFALSE?
C
A.Embodiesbestpracticeandgovernance
B.Isbasedon‘managementbyexception’
C.requiresfixedprogressmeetings
D.promotesconsistencyofprojectwork
12.WhichofthefollowingstatementsisTRUE?
PRINCE2provideswhichofthefollowing?
A
A.Aprojectmanagementmethod
B.Aprogrammemanagementmethod
C.Linemanagementtechniques
D.Alloftheabove
13.WhichofthefollowingstatementsisFALSE?
A
A.Fixedprogressmeetings
B.Delegationofauthority
C.Dividingtheprojectintomanagementstages
D.Timeeventdrivenprogressreporting
14.WhichofthefollowingstatementsisFALSE?
PRINCE2providesprojectswith…D
A.goodcommunicationchannelsbetweenprojectmanagementandtherestoftheorganisation
B.regularreviewsofprogressagainsttheBusinessCase
C.flexibledecisionpoints
D.completeabsenceofdeviations
15.InPRINCE2whatisthenameoftheproductthatisusedtodefinetheinformationthatjustifiesthesettingup,continuationorterminationoftheProject?
A
A.TheBusinessCase
B.TheEndStageApproval
C.TheProjectBrief
D.TheProjectMandate
16.InPRINCE2whatanswersthequestion:
Whyshouldthisprojectbedone?
A
A.TheBusinessCase
B.TheEndStageApproval
C.TheProjectBrief
D.TheProjectMandate
17.WhichoneoftheseisNOTaPRINCE2ThemeC
A.Organisation
B.Quality
C.Product-basedplanning
D.Progress
18.WhichoneoftheseisNOTaPRINCE2Theme?
B
A.Risk
B.QualityReview
C.Plans
D.Change
19.WhichoneoftheseisaPRINCE2Theme?
A
A.Risk
B.QualityReview
C.Product-baseplanning
D.ProductDescriptions
20.WhichoneoftheseisNOTaPRINCE2These?
D
A.Risk
B.Quality
C.Progress
D.DirectingaProject
21.WhichofthesestatementsisFALSE?
A
A.APRINCE2planisbasedonWorkBreakdownStructure
B.APRINCE2planiskeptinlinewiththeBusinessCase
C.APRINCE2planneedsapproval
D.APRINCE2planismorethanabarchartshowingtimescales
22.WhichofthefollowingisareasonfortailoringPRINCE2?
C
A.Ensuringthatthemethodisrelatedtotheproject’senvironment
B.Ensuringtheproject’scontrolisbasedontheproject’sscale
C.Bothoftheabove
D.Noneoftheabove
23.Whichofthefollowingprovidesthevitaltestoftheviabilityofaproject?
B
A.TheProjectFile
B.TheBusinessCase
C.Applicationofspecializedtechniques
D.TechnicalStages
24.WhatenvironmentdoesPRINCE2assume?
B
A.Afixed-pricecontract
B.ACustomer/supplierenvironment
C.Aspecialistenvironment
D.Athird-partyenvironment
25.Whatisdefinedas:
‘theresultofthechangederivedfromusingtheoutputs’?
B
A.Items
B.Outcome
C.Product
D.Theme
26.Completethefollowingphrase…
‘Aprojectisatemporaryorganizationthatiscreatedforthepurposeofdeliveringoneormorebusinessproductsaccordingto…’D
A.Thecustomer’sneeds
B.anagreedcontract
C.theProjectPlan
D.anagreedBusinessCase
27.Aprojectisatemporaryorganizationthatiscreatedforthepurposeofdeliveringoneormore…C
A.Activities
B.Stages
C.Businessproducts
D.Techniques
28.Completedthefollowingphrase…
‘Aprojectistemporaryorganizationthatiscreatedforthepurposeofdeliveringoneormore_____accordingtoanagreedBusinessCase.’B
A.customer’sneeds
B.businessproducts
C.components
D.resources
29.WhatdoesPRINCE2regardascontainingthe‘optimummixofinformationtojudgewhethertheprojectisviable’withinaproject?
D
A.TheRiskLog
B.TheProjectInitiationDocument
C.TheProjectBrief
D.TheBusinessCase
30.WhichconceptsdoesPRINCE2useforseniormanagementinvolvement?
B
A.Managementbyacceptance
B.Managementbyexception
C.Managementbyinvolvement
D.Managementbyconsent
31.WhatdoesPRINCE2offertotheProjectBoardbecausetheirprojectresponsibilitiesareinadditiontotheirnormalwork?
D
A.Managementaccountability
B.Delegationofaccountability
C.Regularprogressmeetings
D.Managementbyexception
32.InPRINCE2terminology,whichphraseisusedtodescribean‘exception’?
B
A.Wheretherehasbeenadeviationbeyondthetolerancelevels
B.Whereitcanbeforecastthattherewillbeadeviationbeyondtheagreedtolerancelevles
C.Anymajorissue
D.Whereariskactuallyoccurs
33.WhichofthefollowingoptionsisdetailedinPRINCE2?
C
A.Peoplemotivation
B.EarnedValueAnalysis
C.Product-basedplanning
D.CriticalPathAnalysis
34.WhichofthefollowingtechniquesispartofPRINCE2?
B
A.EarnedValueAnalysis
B.Product-basedplanning
C.CriticalPathAnalysis
D.Ganttcharting
35.WhichofthefollowingprojectmanagementaspectsisdetailedasathemeinPRINCE2?
C
A.Contracting
B.EarnedValueAnalysis
C.Risk
D.Procurement
36.WhichofthefollowingoptionsisdetailedasathemeinPRINCE2?
B
A.Teamleadership
B.Organisation
C.EarnedValueAnalysis
D.Corporatequalitymanagement
37.HowdoesPRINCE2providesafirmbasisfordefiningthescopeboundary?
C
A.ByestablishingatotallyindependentBusinessCaseforeachproject
B.BykeepinganindependentRiskLogforeachproject
C.Byidentifying,definingandanalyzingtheprojectsproducts
D.BydefiningtheBusiness/User/Supplierroles
38.ThePRINCE2approachtoprojectmanagementis:
A
A.Process-based
B.Component-based
C.Technique-based
D.Control-based
39.Whichofthefollowingstatementsis/arecorrect?
C
1.PRINCE2issuitableforbothsmallandlargeprojects
2.PRINCE2canbeappliedregardlessoftheindustryorfieldofwork
A.Onlythefirst
B.Onlythesecond
C.Both
D.Neither
40.Considertheassertionsgivenbelow:
aretheassertionstrue?
B
1.Asaprojectmanagementmethod,PRINCE2isalsosuitableforprogrammemanagement
2.ThePRINCE2methodisnotdependentontheareaofapplication
A.Onlythefirstassertionistrue
B.Onlythesecondassertionistrue
C.Botharetrue
D.Neitheraretrue
41.WhichofthefollowingthreestatementsaretrueofaPRINCE2project?
D
1.Thereisnostandardapproachtoaproject
2.ActivitiesdowntothelevelofWorkPackageareidentifiedduringProjectInitiation
3.Aprojectisatemporarystructure
A.Only1and2
B.Only1
C.1,2and3
D.Only3
42.PRINCE2assumesaCustomer/Supplierenvironmentandiswrittenfromwhichstandpoint?
A
A.Thesetwoparties/mayormaynotbepartofthesameorganisation
B.Thesetwopartieswillsharecommonsenormanagement
C.Thetwopartieswillsharethesamebusinesscase
D.Thetwopartiesmustcomefromcommerciallyseparateorganisations
43.Whichofthefollowingstatementsis/arecorrect?
B
1.PRINCE2isdesignedtobeusedonanytypeofproject
2.ThewayinwhichPRINCE2isappliedtoeachprojectmustbethesame
3.Tailoringthemethodtosuitthecircumstancesofaparticularprojectiscriticaltoitssuccessfuluse.
A.Onlythefirsttwo
B.Onlythefirstandthird
C.Allofthem
D.Onlysecondandthird
44.Whichofthefollowingstatementis/arecorrect?
C
1.PRINCE2isdesignedtobeusedonanytypeofprojectinanyenvironment
2.ThewayinwhichPRINCE2isappliedtoeachprojectcannotvary
3.Enforcingthemethodinspiteofthecircumstancesofaparticularprojectiscriticaltoitssuccessfuluse
A.Onlythefirsttwo
B.Onlythefirstandthird
C.Onlythefirstone
D.Onlythesecondandthird
45.WhichrolefromthefollowinglistdoesPRINCE2sayca