机房搬迁标准方案Word文档格式.docx
《机房搬迁标准方案Word文档格式.docx》由会员分享,可在线阅读,更多相关《机房搬迁标准方案Word文档格式.docx(45页珍藏版)》请在冰点文库上搜索。
搬迁时间要求.............................................................................................................................................
6
3.
搬迁实施方案....................................................................................................................................................
3.1
总体方案.....................................................................................................................................................
3.2
搬迁前准备工作.........................................................................................................................................
7
3.2.1
机房环境检查....................................................................................................................................
3.2.2
搬迁设备统计....................................................................................................................................
8
3.2.3
系统关联性分析................................................................................................................................
3.2.4
系统拓扑结构....................................................................................................................................
3.2.5IP地址规划.......................................................................................................................................
9
3.2.6
设备位置规划....................................................................................................................................
3.2.7
系统健康检查..................................................................................................................................
10
3.2.8
机房网络系统建设..........................................................................................................................
3.2.9
新机房主机系统建设......................................................................................................................
3.2.10
设备标签制作................................................................................................................................
11
3.2.11
搬迁物流方案................................................................................................................................
3.2.12
搬迁通知........................................................................................................................................
3.3
搬迁实施...................................................................................................................................................
12
3.3.1
现场环境保护..................................................................................................................................
3.3.2
数据备份..........................................................................................................................................
3.3.3
系统停机..........................................................................................................................................
3.3.4
搬迁设备拆卸、清点......................................................................................................................
13
3.3.5
监督设备搬运过程..........................................................................................................................
3.3.6
目的地设备清点、拆包、上架......................................................................................................
3.3.7
设备功能恢复..................................................................................................................................
3.3.8
启动应用系统..................................................................................................................................
14
3.3.9
系统功能测试..................................................................................................................................
3.4
搬迁后系统保障.......................................................................................................................................
4.
方案关键步骤...................................................................................................................................................
15
4.1搬迁技术方案必须周密细致、切实可行。
..............................................................................................
4.2
提前预测搬迁风险。
.................................................................................................................................
4.3
充分调动一切资源。
4.4
采用流程化搬迁方式。
.............................................................................................................................
16
4.5
做好系统的充分验证。
5.
风险及应对措施..............................................................................................................................................
17
6.
应急预案..........................................................................................................................................................
19
6.1.1搬迁过程中设备硬件损坏................................................................................................................
6.2
设备开机无法正常运行...........................................................................................................................
第2页共27页
附件一:
现机房设备安装情况统计表20
附件二:
现机房设备机柜安装图21
附件三:
现有网络拓扑图22
附件四:
现有网络设备连接图23
附件五:
新机房机柜布局图24
附件六:
新机房设备机柜安装图25
附件七:
新机房网络拓扑图26
附件八:
新机房设备连接表(规划)27
第3页共27页
1.概述
1.1项目背景
华康医院现有机房位于医院的4楼,随着业务的发展现机房因供电及基础环境风险
极高、机房容量不足等原因,选择在原址进行改造。
原机房面积约约34平方米。
标准
拟满足信息系统基本运行、监测、控制的应用要求。
规划设计上需预留一定升级扩容空
间,并根据医院现场情况进行相应调整,使用年限需达到五年以上。
本次建设重点在布
局重整、电力供配、温湿度控制上。
全面建设好新机房以达到标准化机房建设要求,并
保证机房改造过程中现有系统运行风险降到最低。
本院搬迁项目主要分为:
设备的搬迁,设备上架,设备安装调试等服务。
1.2项目目标与原则
1.2.1项目目标
华康医院机房搬迁项目,需要将原有机房改造及设备搬迁,我司需保障原有设备在
拆除、搬迁及安装过程中安全无损,保障其在新机房的投入使用,其中涉及系统有计算
机及网络设备、安防设备、环境监测设备、空调新风设备等。
主要实现以下目标:
1、现状详细梳理。
对现有信息系统的现状进行详细整理,梳理清楚现有机房内设
备状况、设备和应用之间的对应关系、设备连接关系、信息点状况、信息系统架构、应
用关联关系、应用服务要求等基础信息,形成当前IT系统的详细勘察报告,为本次搬
迁策略的制定以及后期系统的维护提供重要的基础信息。
2、新机房合理规划。
满足现有设备搬迁运行需求并考虑较长时期内业务发展需求,
结合搬迁按设备类型、热量排放、网络分区、应用分类等规划设备部署。
3、业务平稳迁移。
通过风险分析、应用关联分析、业务影响分析,制定安全有效
的整体搬迁策略,减少业务影响,减少业务中断次数与时间,规避搬迁风险,保障业务
连续性;
制定充分、细致的搬迁实施方案,提供与搭建应急环境,进行充分详细的准备
工作,根据搬迁策略,将业务系统顺利迁移回整改后的新机房。
4、资源有效投入。
充分利用现有设备,控制新投入设备费用,分析需求在关键点
第4页共27页
合理投入过渡及更新设备,降低搬迁风险、提高整体运维水平。
5、搬迁周期可控。
在可控的范围内尽量缩短新老机房并行周期,充分分析业务、
存储、网络等各种关联分几批有计划搬迁。
1.2.2建设原则
系统搬迁过程中遵从安全性原则、先进性原则、开放性原则、高可靠性原则、可管
理性原则。
1、安全性原则:
在工程实施过程中,应通过安全技术和措施保证网络和系统的安
全性、数据的安全性、用户访问的安全性,在技术保障的同时,从管理层面加强安全性
管理。
2、先进性原则:
系统搬迁过程中的新购及过渡软硬件产品应采用先进的、开放的
系统结构;
应可通过智能化的网络设备及网管软件实现对系统的有效管理与控制;
工程
应采用先进的现代管理方法,以保证项目实施与管理的科学性。
3、开放性原则:
系统搬迁过程中的新购及过渡软硬件产品应遵循开放性和标准化
基本原则,所选用的硬件设备、软件等必须遵循相应的国际标准,保证系统具有互操作
性和开放性。
各系统之间采用优化的原则,使各系统之间更好地配合,达到最佳的应用
效果。
4、高可靠性原则:
搬迁过程应满足各系统维护及业务部门高可靠性及高稳定性的
要求。
5、可管理性原则:
搬迁过程应保证系统的可管理、实施过程的可管理、实施风险
的可控制。
2.需求分析
2.1搬迁设备需求
本次搬迁包括本医院机房内所有的IT系统,迁移设备包括服务器、交换机、网络
设备、安全设备等。
涉及搬迁的设备清单如下表:
第5页共27页
现机柜配置:
共计
8个机柜,具体如下:
序号
名称
数量
备注
1
综合布线柜
2
楼层骨干级联、外线接入、四楼水平配线、
电话线路
网络设备柜
核心交换设备
3
视频前端柜
院内有线电视转换前端
移动终端机柜
中国移动线路接入及终端设备
(32U)
医疗业务服务器
医疗业务系统
柜
表2.1-1
搬迁设备清单
原机柜位置
机型
设备用途
U数
电源接口数
序列号
A机
cisco
catalyst
1u
2960
A12U
A18U-20U
AVAYAG450
3u
A22U-23U
dellPER710
2u
A25U-26U
IBMX3650M3
2.2搬迁时间要求
要求在2017年*月*日下午下班后开始搬迁,22日8:
00完成现机房内全部IT设备
至新整改机房的搬迁,并恢复系统的正常运行。
其中网络部分要求在19日全部恢复正
常运行。
3.搬迁实施方案
3.1总体方案
根据现场调研,目前机房内涉及搬迁的设备除个别设备外均处于在线运行使用状
第6页共27页
态,且旧、临时机房不考虑并行一段时间,因此必须在一次系统停机时间段内完成全部
设备的搬迁工作。
即,从某年9月18日18:
00停机后,至某年9月22日12:
00前为搬迁时间窗口,在该时间段内完成旧机房所有IT设备至新整改机房的搬迁及系统恢复工作。
在某年9月18日之前,需要完成机房的建设(装修、强电、弱电、空调、消防、安防等)、机房网络系统建设(局域网、互联网、专网等)、机房主机系统建设(存储、核心业务备机系统)、现机房运行系统健康检查、物流准备(搬迁环境、路线考察,物流方案制定等)等前期准备工作。
在某年9月18日搬迁开始后,首先停止业务系统的对外服务,之后进行系统数据的备份,然后进行系统停机。
在某年9月19日12:
00前完成搬迁系统网络部分的恢复上线,使系统能够正常提供服务。
在某年9月22日8:
00前完成所有业务系统的恢复上线,使系统能够正常提供服务。
在搬迁完成后,进行系统功能测试,并安排技术人员进行现场值守,保障系