陕西省西咸新区空港新城沣泾大道道路及排水工程招标施工组织设计.docx
《陕西省西咸新区空港新城沣泾大道道路及排水工程招标施工组织设计.docx》由会员分享,可在线阅读,更多相关《陕西省西咸新区空港新城沣泾大道道路及排水工程招标施工组织设计.docx(84页珍藏版)》请在冰点文库上搜索。
陕西省西咸新区空港新城沣泾大道道路及排水工程招标施工组织设计
施工组织设计·······················································5
第一章:
工程概述···················································5
一、工程编制依据···············································5
二、编制原则···················································5
三、工程概况···················································6
四、施工技术要求···············································6
第二章:
施工总体布署···············································7
一、施工准备工作···············································7
1.现场组织机构··············································7
二、施工总体规划···············································7
1.总工期安排················································7
2.管理方针··················································8
3.施工总体布署··············································8
4.临时工程··················································9
①临时用水················································9
②临时用电················································9
③临时设施················································9
第三章:
拟投入本工程的主要施工机械及进场计划·······················9
一、项目部任务划分及进度安排···································9
二、施工机械准备················································10
1.机械准备情况及表·········································10
2.材料准备情况及表·········································11
3.劳动力安排计划表·········································12
第四章主要项目的施工方案及施工方法································13
一、路基工程····················································13
(一)、路基土方工程············································13
1.施工准备················································13
2.施工方案及方法···········································13
3.土方开挖施工要点·········································13
4.土方填方施工要点·········································14
5.压实工艺·················································14
二、排水工程施工方法············································15
(一)施工工艺流程图············································15
(1)、排水工程项目············································15
(2)、污水管道施工方法·······································15
(3)、雨水管道施工方法·······································17
1.技术准备················································17
2.材料设备要求············································17
3.作业条件················································18
(4)、施工工艺···············································19
a.工艺流程···············································19
b.操作工艺···············································19
(5)、管道安装················································24
(6)、检查井··················································24
三、道路工程··················································25
1.总体施工注意事项·········································25
2.总体施工程序·············································25
3.道路路基路面结构层·······································26
3.1道路路基施工方法及路基填筑工艺图························26
3.2石灰土施工方法··········································27
3.3二灰碎石施工方法········································28
3.4沥青混凝土面层施工方法及技术要求·······················29
路面施工工艺图·········································32
四、道路附属工程施工方法········································34
1.道路侧石、平石及人行道砖铺设施工························34
(1)、道路侧石、平石施工工艺······························34
(2)、人行道砖的施工·····································34
2.人行道面砖铺砌施工·····································35
3.中央分隔带和道路;两侧红线内场地平整施工··················35
第五章:
冬、雨季施工注意事项与保证措施····························36
1.冬季施工·················································36
2.雨季施工················································37
第六章:
确保工程质量的技术组织措施··································38
一、技术保证措施················································38
1.建立一套完整的技术管理体系······························38
2.编制作业指导书及技术交底制度····························38
3.坚持“三检”、“三不交接”和“五不施工”制度····················38
4.坚持隐蔽工程检查签证制度·································38
5.坚持测量资料换手复核制度·································38
6.施工过程的质量检测制度···································38
7.建立原材料半成品、成品采购及验收制度·····················38
8.仪器设备的检定制度·······································39
9.施工资料管理制度··········································39
二质量保证措施·················································39
1.质量保证体系··············································39
2.保证质量的各项管理措施····································39
3.严格按规范施工的措施······································40
4.保证施工人员操作技能的措施································40
5.保证物资、设备管理的措施···································41
6.工序过程质量的控制·······································41
7.竣工阶段质量的保证措施····································41
8.保证质量的施工技术措施···································41
三、工期保证措施···············································44
第七章:
安全施工措施···············································44
1、编制依据·················································44
2、安全目标·················································44
2.1人身安全目标··········································44
2.2工程安全目标··········································44
3.本工程安全工作重点········································44
4.安全管理体系·············································44
4.1建立完善的安全管理组织机构····························45
4.2合理配置专职安全管理人员······························45
4.3建立完善的安全管理制度································45
4.3.1安全生产责任制······································45
4.3.2安全技术交底责任制度································47
4.3.3安全教育制度········································47
4.3.4安全检查制度········································47
4.3.5安全员跟班作业制度··································47
4.3.6安全警示制度·······································47
4.3.7事故处理制度报告····································47
4.3.8班前安全活动制度····································48
4.3.9持证上岗制度········································48
4.3.10安全例会制度·······································48
4.3.11安全培训制度·······································48
5.消防措施及应急预案········································48
5.1消防措施··············································48
5.2火灾应急预案··········································49
5.2.1火灾应急预案通则····································49
5.2.2详细应急预案········································49
6.防汛措施及应急预案········································50
6.1防汛措施··············································50
6.2防汛抢险预案··········································51
7.其它应急预案·············································51
7.1发生食物中毒事件的应急预案····························51
7.2发生机械伤害和触电事件的应急预案······················52
8.主要分项作业安全技术措施··································52
8.1路基安全技术措施······································52
8.2排水工程施工安全技术措施······························52
9.安全用电措施·············································53
10.管线保护·················································54
11.社会人员安全保障措施·····································54
第八章:
文明施工措施··············································55
1.施工现场管理··············································55
2.施工秩序管理·············································55
3.施工安全管理·············································56
4.施工卫生管理·············································56
5.环境保护管理·············································57
5.1环境保护措施············································57
5.2环境保护的重点··········································57
5.3环境保护体系············································57
5.3.1环保工作职责··········································57
5.3.2环保施工措施··········································58
6.成品保护·················································60
7.其它措施··················································60
7.1消防保卫措施············································60
7.2健康保障措施············································60
施工总平面图
施工组织设计
第一章工程概述
一、编制依据
(1)陕西省西咸新区空港新城沣泾大道道路及排水工程招标文件。
(2)依据西安市政设计研究院设计的“陕西省西咸新区空港新城沣泾大道(空港南环路—第一大道)市政工程施工图设计”图纸中的道路、排水工程等施工图纸中的全部内容。
(3)依据现行公路施工规范和相关的技术标准。
(4)根据我方对工程现场的踏勘情况及我方所拥有的技术、设备、资金等各方面的具体情况。
(5)引用规范及标准
①《公路工程技术标准》(JTGB01-2003);
②《公路路基施工技术规范》(JTGF10-2006);
③《公路路面基层施工技术规范》(JTJ034-2000);
④《公路沥青路面施工技术规范》(JTGF40-2004);
⑤《公路工程质量检验评定标准》(JTGF80/1-2004);
⑥《城市道路工程质量检验标准》(DB29-50-2003);
⑦《西安市市政工程质量检验评定标准(道路工程)》;
⑧《西安市市政工程质量检验评定标准(排水工程)》;
⑨《给水排水管道工程施工及验收规范》(GB50268-97);
⑩《城市排水工程质量检验标准》(DB29-52-2003);
⑾《施工现场临时用电安全技术规程》(JGJ46-2005);
⑿《建筑机械使用安全技术规范》(JGJ33-2001);
⒀《建筑施工高处作业安全技术规范》(JGJ80-91);
⒁《建筑施工扣件式钢管脚手架安全技术规程》(JGJ130-2001);
⒂《建筑施工门式钢管脚手架安全技术规程》(JGJ128-2000)。
二、编制原则
1.遵循招标文件条款的原则。
在编制施工组织设计文字说明、附图、附表中,严格按照招标文件规定,做到统一标准、规范编制。
2.遵循设计图纸、施工规范、规程、验收标准的原则。
在编写主要项目施工方法中,严格按设计图纸要求,执行现行施工规范、规程及验收标准,确保工程质量。
3.坚持实事求是的原则。
在制定各具体工程项目实施方案过程中,充分研究、分析本工程的特点、难点,坚持科学组织、合理安排、均衡生产,确保优质高效完成本标段建设任务。
4.坚持施工全过程严格管理的原则。
在各道工序施工中,认真自检,严格执行监理工程师指令,尊重业主和设计代表意见,严格管理。
5.坚持推广应用“四新”成果的原则。
在施工中积极推广应用新技术、新材料、新工艺、新设备,充分发挥科学技术在施工中的先导作用。
6.合理地选择施工方案,应用科学的计划方法,确保施工安全,降低工程成本,提高施工质量。
7.坚持专业化作业与综合管理相结合的原则。
在施工组织安排上,以专业队为基本组成形式,机械化作业为主,充分发挥专业人员和先进优良设备之优势,并采取综合管理手段合理配置,以达到整体优化目的。
8.实施项目法管理,利用网络技术对生产资源及生产诸要素进行优化配置,保证实现成本、工期、质量、安全及社会信誉等预期目标。
三、工程概况
陕西省西咸新区空港新城沣泾大道市政工程为西咸新区骨架网中的一条城市快速路,道路等级为城市快速路,设计车速80km/h。
工程范围:
空港南环路东段,西起沣泾大道,东至空港旅游路,全长2183.238米,规划红线宽60米,主要包括道路、雨、污水、交通及照明工程属新建的城市主干路,沥青混凝土路面。
修建施工桩号(K0+084.643-k2+179.206),道路红线宽为60米,两侧各(14.5米机动车道+2.5米绿化带+4米非机动车道+4米人行道)。
新城中大道西段,西起空港南环路东段,东至新城六路,全长561.921米,规划红线宽度为45米,属新建的城市主干路,沥青混凝土路面。
主要包括道路、雨、污水、交通及照明工程。
修建施工桩号(K0+046.615-K0+595.869),正常段道路红线宽为45米,两侧各(10.5米机动车道+2米绿化带+3.5米非机动车道+4.5米人行道),渠化段道路红线宽为52米,两侧各(14米机动车道+2米绿化带+3.5米非机动车道+4.5米人行道)。
新城六路,西起新城一路,东至新城中大道,全长537.922米,红线宽度为36米,数新建的城市次干路,沥青混凝土路面。
主要包括道路、雨、污水、交通及照明工程。
修建施工桩号(K0+265.816-K0+500.537)正常段道路红线宽度为36米,两侧各(10.5米机动车道+1.5米绿化带+3米非机动车道+3米人行道),渠化段道路红线宽为43米,两侧为(14米机动车道+1.5米绿化带+3米非机动车道+3米人行道)。
沣泾大道(K0+000~K4+4833.583)道路工程、排水工程所包括的施工内容。
道路全长4833.583米,红线宽度100米,主道双向8车道,辅道双向4车道,中央分隔带两侧预留BRT车道。
雨水管线主管道长度3545米,支管长度5977.8米。
污水管道主管道2085米,支管长度2890米。
污水管径d400-1350,雨水管径d500-2200。
本工程质量为合格标准。
本工程工期为360天。
四、施工技术要求:
1、严格按照设计图纸要求施工,凡图纸未提及的技术要求均应符合国家有关的施工和验收规范。
2、根据甲方提供的控制点校核后进行定位测量和高程测量,并向甲方提交测量报告,经验线合格后方可正式开工。
3、所有隐蔽工程的施工都需现场监理工程师验收合格后,经甲方确认后方可进行下道工序的施工。
4、根据设计文件及施工现场条件制定施工方案,编制确实可行的施工组织设计。
5、根据国家质量评定标准,在开工前向甲方质监部门报送单位工程的分部分项工程质量检验表格样式,并在施工期间实事求是、及时认真地填报,以便有关部门随时检查,做为竣工验收评定该项工程质量的依据。
6、充分了解施工现场和周围环境条件,以免破坏地下管