桩基试桩工程施工技术方案英文对照
Catalogue
第一章ChapterOneExplanation&References1
一、Explanation1
二、References1
三、GeneralSituation2
3.1BasicCondition2
3.2DesignCondition3
3.3SurroudingEnvironment3
3.4GeneralGeologicalCondition4
四、DifficultiesandCountermeasures4
4.1Thefilledearthisthickandwillinfluenceonpilefoundationconstruction.4
4.2Thesiteexistundergroundsilt,whichaffectsthepilequality.5
五、ConstructionDeployment6
5.1ConstructionLayout6
5.2TemporaryElectricity7
5.3LaborPlan7
5.4MaterialManagement7
5.5ConstructionOrganizationandHumanResource8
六、Projectscheduleandassurancemeasures10
6.1ScheduleGoals10
6.2PlanforTrialPilingStage10
6.3ProjectSchedule11
ChapterTwoMainconstructionprocessandtechnicalmeasures12
一、Bored Pile ConstructionScheme12
1.1ConstructionTechnologyProcess12
1.2Mainconstructiontechnicalmeasures13
ChapterThreeMainConstructionMeasures19
一、SeasonalConstructionMeasures19
1.1ConstructionMeasuresinWinter19
二、QualityControlMeasure19
2.1QualityAbject19
2.2QualityResponsibilitySystem19
2.3QualityControl20
三、SafetyandCivilizedMeasures21
3.1CivilizedMeasures21
3.2SafetyMeasures23
四、EnvironmentalProtectionMeasures24
4.1EnvironmentalProtectionPurpose24
4.2ContinuousImprovementandPollutionPrevention.24
4.3RegulationofEnvironmentalProtection.25
五、FireManagementMeasures25
六、RelevantCooperationMeasures26
七、ProjectAcceptanceScheme26
八、Appendix27
1-Constructionschedule
2-Layoutofconstructionsite
3-Listofmainequipments
附件4-《拟投入劳动力计划表》Laborschedule
4-《其他文件》OtherDocuments
ChapterOneExplanation&References
一、Explanation
ThisschemeisforthetrialpilingdirectcontractworksofXXXXproject.Themaincontentfortheprojectistheprophasetestpileconstruction.
二、References
Thistechnologyschemebasedprimarilyonthetenderdrawings,engineeringinvestigationmaterialandtechnicalspecification.Itiseditedrefertothetechnicalspecificationinreferenceandincombinationwithourcompanyinthesuccessfulexperienceofsimilarprojectconstruction.Theprojectobjectivesisaroundtoensuresafety,qualityoftheconstruction,periodandreducecost.
主要依据的文件如下:
Themainreferencesisasfollows:
2.1Biddingdocumentanddrawings;
2.2Relatedtechnicaldocumentandtheconstructiontechnicalcodesoncurrent.
2.3Themaincodes executedinconstruction:
《Codefordesignofbuildingfoundation》(GB50007-2011)
《Codeforengineeringsurvey》(GB50206-2007)
《Codeforacceptanceofconstructionqualityofbuildingfoundation》(GB50202-2002)
《Codeforacceptanceofcongstructionalqualityofconcretestructures》(GB50204-2011)
《Hotrolledplainsteelbarsforthereinforcementofconcrete》(GB1499.1-2008)
《Hotrolledribbedbarsforthereinforcementofconcrete》(GB1449.2-2007)
《Unifiedstandardforconstructionalqualityacceptanceofbuildingengineering》(GB50300-2001)
《Standardforevaluationofconcretecompressivestrength》(GB/T50107-2010)
《Thecodeofconstructionprojectmanagementbyenterprisesofconstructionindustry》(GB/T50326-2006)
《SpecificationforConstructionofBoredCast-in-PlacePille》(DB/TJ08-202-2007)
《Specificationforweldingandacceptanceofreinforcingsteelbars》(JGJ18-2012)
《Specificationformixproportiondesignofordinaryconcete》(JGJ-55-2011)
2.4TheGeologicalinvestigationreportofthisproject.
2.5Otherinformationprovidedbythetenderee.
三、GeneralSituation
3.1BasicCondition
ProjectSummary
TENDEREE
XXXXXXX
PROJECTNAME
XXXXXX
PROJECTSITE
XXXXXX
PILEDESIGNUNIT
XXXXXXX
PROSPECTINGUNIT
XXXXXX
PROJECTSCALE
PROJECTSCOPE
Thecontentsoftheworkrequiredbythetenderdocuments.
CONSTRUCTIONPERIOD
TheprojectisscheduledtostartonXXXX,andcompleteonXXXXX
3.2DesignCondition
前期试验桩主要设计概况如下:
序号
项目名称
单位
工程量
备注
1
桩径Φ600mm桩长53.45m
根
2
桩径Φ600mm桩长53.45m
根
3.3SurroudingEnvironment
3.3.1ProjectSite
ThisprojectislocatedinChangNingdisteictofShanghai.easttoXXXRoad,SouthtoXXXXRoad,westtoXXXXRoad,northtoXXXXRoad.
ProjectLocation
3.3.2TheSurroundingEnvironment
Accordingtothebiddingdocument,combiningwiththesitesurvey,thesiteenvironmentoftheprojectisdescribedasfollows:
ProposedsiteisnorthtoXXXXRoad,itisabout35.0metersbetweentheroadandthefoundationpitedge.Theotherthreesidesarealladjacenttotheroad.Theroads,residentialandcommercialbuildingsaroundtheproposedsite,lotsofpipelinesundergroundetc.Onthewhole,thesurroundingenvironmentofthisprojectiscomplicated.
3.4GeneralGeologicalCondition
RefertotheGeotechnicalinvestigationreport.
四、DifficultiesandCountermeasures
4.1Thefilledearthisthickandwillinfluenceonpilefoundationconstruction.
4.1.1Difficulty
BaseontheGeotechnicalinvestigationreport,theproposedsitehasthickfilledearth,theaveragethicknessisabout1.50to3.70m.Thefilledearthislooseandhascomplicatedcomposition,unevenquality.
4.1.2Countermeasure
(1)Deviationbetweenthecenterofpilecasingandthecenterofpileshouldnotbegreaterthan50mm,theclayshouldbefilledoutsideofthepilecasingandpackedinlayers.
(2)Duringdrilling,controlthedrillingparameters,expeciallycontrolthedrillingspeedandpreventthedrillinginclination.
(3)Duringdrilling,strictlycontrolperformanceofthemudtoensuretheeffectofboreholeprotectionandpreventtheboreholecollapseinloosedfilledearth.
4.2Thesiteexistundergroundsilt,whichaffectsthepilequality.
4.2.1Difficulty
Accordingtogeotechnicalinvestigationreport,theproposedsiteexistundergroundsilt,thedepthisabout2.20to4.20m,theundergroundsiltcontainsfilledsoil,organicmatter,plantroots,cindergraveletc.,ashblackandhavebadsmell,theundergroundsiltmayaffectthequalityofpile.
4.2.2Countermeasure
(1)Themeasureofreplaceandbackfillsoilwillbetakenintheundergroundsilt.Inordertoreducetheamountofworkandunnecessarymechanicalconstruction,theslopeshouldbereduced.Ifthelocalslopeislarge,itwillbetakentomaketwoorthreesteps,thestepsareeasytolowerdown,eachstephasenoughwidth,convenienttoexcavatetheconstructionwork.
(2)Usetheexcavatortodesilttheundergroundsilt,andthemudwillbetransportedafter.
(3)Cleansoilbackfillwillbecarriedoutintheareaafterdredging.Whenbackfilling,thepackingelevationiscontrolledbythestratifiedcontrolofthepavement.Thethicknessofthepackinglayershouldnotgreaterthan1m.
五、ConstructionDeployment
5.1ConstructionLayout
Accordingtotheprojectbiddingdocuments,theactualsituationandprogressrequirements,constructionsitemustbereasonabledeployed,thespecificprinciplesareasfollows:
(1)Accordingtotheconstructionscheduleofthisproject,thesitelayoutwillbeadjustedindifferentconstructionstages.
(2)Thelayoutofproductionfacilitiesshouldbeconvenientforconstructionandproductionarrangement,andmeetstherequirementsoffireprotectionandlaborprotection.
(3)Meettherequirementsoftheconstructionunitforthelayoutoftheconstruction,adjusttheshiftofthewarehouseyardintheconstructionareawhenitisnecessary.
(4)Thelayoutfortheconstructionshouldnotdamagethesurveyingmarkersandshallnotaffectthepass-throughconditionsofthesurveyingmarkers.
(5)Effectivedrainagesystemwillbeestablishedintheconstruction,dailymaintenancisnecessarytopreventsurroundingroadsurfacecontamination.
5.2TemporaryElectricity
Duringthetrialpilingwork,thepowerwillbesuppliedbygeneratorpower,powertransmissioniscompletedbyfivecorecablewithrubbersleeve,theelectricitywillbetransferedthroughthegeneratortofixed200a~250aelectricityboxwhicharedecoratedintheconstructionsite.Alloftheelectricityusinginconstructionisconnectedfromfixedelectricityboxtoeachelectricitylocation.
5.3LaborPlan
Thepersonnelconfigurationofthemainconstructionoftestpileconstructionisshowninschedule4-laborschedule.
5.4MaterialManagement
Inordertoensurethequalityofthematerialsrequiredfortheproject,thematerialmanagementregulationsareasfollows:
5.4.1Materialplanandprocurement
Materialplanwillbeestablishedaccordingtotheapprovedconstructionscheduleplan,intheplanthenameofmaterial,thespecification,thequantityandroughlyentrydatewillbenoted.Materialswithspecialqualityrequirementsshouldbereportedtothesupervisorandtheconstructors.
5.4.2AcceptanceofMaterial
(1)Intheprocessofmaterialsacceptance,thematerialmanagershallfirstverifythequality certificatesofmaterials,includingthefactorycertification,productioncertificationandthecopyofthepermitforproductionlicense.
(2)Thematerialsneedtoberetestedshouldbecheckedandacceptedstrictly.
5.5ConstructionOrganizationandHumanResource
5.5.1ConstructionOrganization
Ourcompanywillformaout-standingprojectdepartment,theprojectdepartmentfollowtheprincipleoftheprojectmanagerresponsibilitysystem,equippedwithenoughmanagersfordifferentaspects.Theorganizationchartisasfollows:
Logisticsdepartment
Constructiondepartment
Technicaldepartment
ProjectManager
Financedepartment
Businessdepartment
Generaloffice
Safetymanagement
Engineeringmagement
Company
Theorganizationchart
5.5.2TheMainManagerResponsibilities
(1)ProjectManager
1)Responsiblefortheconstructionandmanagethetheprojecttoensureprojectconstructionbecompleted.
2)Allocateprojectresources,reviewqualifiedmaterialsupplier,auditqualificationandsi