香港理工大学SQA计划文档
NOAA
NationalEnvironmentalSatellite,Data,andInformationService(NESDIS)
ComprehensiveLargeArray-dataStewardshipSystem(CLASS)
QualityManagementPlan
CLASS-1006-CLS-PLN-QM
February1,2005
1DocumentHistory
QualityManagementPlanDocumentHistory
Version
DateCompleted
DescriptionofChange
1.0
07/19/02
InitialRelease
1.1
08/19/02
Modificationsmadefrominternalreview.
1.2
08/29/02
Modificationsmadefrominternalreview.
1.3
10/04/02
ModificationsmadefromCPMTreview.
1.4
11/26/02
AddedcompletedTableB
2.0
09/05/03
Updatedforyearlyreviewandprocessimprovement.
2.1
09/12/03
UpdatedtocorrectcommentsfromCSCRESQMandprojectsreviews.
2.2
09/16/03
Updatedversionnumbertomatchmanagementapprovalofdocument.
2.3
09/29/03
UpdateddocumentperassociatedcommentsbyRichardReynoldsontheMPMPandOSDPDAPdocuments.UpdatedNESDISCIOtoNESDISOSDPM.
2.4
10/27/03
UpdatedbasedonSEPGcommentsandCSCQMreorganization.
2.5
01/17/05
Yearlyupdate,addintergroupactivities,updatemeasurementsinformation,lessonslearned.
3.0
02/01/05
ApprovedbyCPMT;minorformatchangesadded
2ReviewandApproval
QualityManagementPlanReviewHistory
Reviewer
VersionReviewed
Date
CSCQMO
2.5
02/01/05
CLASSSEPG
2.5
01/24/05
CPMT
2.5
02/01/05
3Contents
DocumentHistoryii
ReviewandApprovaliii
Contentsiv
ListofFiguresandTablesvii
Section1-Introduction1
1.1Purpose1
1.2Scope1
1.3DocumentOrganization1
1.4ReferencesandRelatedDocuments2
1.5DocumentMaintenance3
Section2-QualityManagementResponsibilities4
2.1QualityObjectives4
2.2QualityManagementOrganization4
2.3QualityManagementOfficeFunctionsandResponsibilities5
2.4QualityManagementResponsibilitiesofOthers6
2.4.1CLASSProjectManagementTeam(CPMT)7
2.4.2TechnicalAreaLeads7
2.4.3LeadIntegrator7
2.4.4SoftwareEngineeringProcessGroup(SEPG)7
2.4.5ProjectTechnicalStaff7
2.4.6CSCFederalSectorGroupQualityResponsibilities8
Section3-QualityManagementApproach9
3.1KeyQualityManagementConcepts9
3.2OverviewofQualityManagementMethodsandActivities9
3.3LifeCycleActivities10
3.4ProcessAssuranceCycle10
3.5EvaluationCriteriaandStandards12
3.6StandardsandProcedures(S&Ps)13
3.7ProductReviews13
3.7.1PeerReviews13
3.7.2QMODeliverableReviews14
3.8ProcessAudits14
3.9Training15
Section4-CLASSQualityRecordsandReports17
4.1ProjectFileRecords17
4.2MonthlyStatusReports17
4.3AuditReports17
4.3.1GeneralAuditReports17
4.3.2PACReports18
4.4Non-ConformanceReportingandCorrectiveAction18
4.5QualityMeasurement19
4.5.1SoftwareQualityGoals19
4.5.2MeasurementandAnalysis19
AppendixA-QMScheduleandMetrics21
AppendixB–DistributionofQualityResponsibilities22
AppendixC–Glossary27
AppendixD-Acronyms29
4
ListofFiguresandTables
Figures
Figure2-1.QualityManagementRelationships5
Tables
Table3-1.QualityActivityScheduleForm10
Table4-1.QualityMetrics20
TableA-1.QualityManagementScheduleofActivities21
TableB-1.DistributionofQualityResponsibilities23
5Section1-Introduction
1.1Purpose
ThepurposeofthisQualityManagementPlan(QMP)istoestablishthegoals,processes,andresponsibilitiesrequiredtoimplementeffectivequalitymanagementfunctionsfortheNOAA/NESDISComprehensiveLargeArray-dataStewardshipSystem(CLASS)project.QualityManagement(QM)identifiesboththeunderlyingconceptsonwhichtheplanisbasedandthespecificactivitiesconductedtoensure:
∙Thebusinesssolutionactivities,suchasfunctionalrequirements,technicalconstraints,systemdevelopment,andmaintenanceactivities,areaccomplishedinaccordancewiththeapprovedmethodology,supportingstandardsandprocedures,and
∙TheproductsandservicesproducedconformtoapplicableCLASSprojectrequirements.
1.2Scope
ThisQMPlanappliestoallsystemdevelopmentandmaintenanceefforts,includingthosetasksperformedbysubcontractors,andcoversallapplicablelifecyclephases.
ThisplanisintendedforusebyallCLASSpersonneltounderstandandperformthequalityactivitiesapplicabletotheirresponsibilities.Qualitymanagementrequirestheprojecttoidentifyqualityactivitiesforitscurrentlyplannedworkphaseandrelatedreleases.
.CLASSprojectmanagementandtheQMOisaccountableforqualityandtheresponsibilitiesandactionsthatdetermineandimplementpolicies.Qualitymanagementincludesobtainingthecommitmentoftheorganization,marshalingresources,andensuringqualityobjectivesandprocessesareusedandsupportedeffectively.
Qualitymanagementfortheprojectisplannedalongwithotherprojecttasksandinitiatives.ImplementationofandcompliancewiththeQMPisthesharedresponsibilityofallprojectpersonnel.BothprojectmanagementandtechnicalstaffarethusintegratedwithandcommittedtothesuccessofoverallQualityManagement.
1.3DocumentOrganization
Thisprojectqualitymanagementplanningdocumentisorganizedasfollows:
∙Section1,Introduction,outlinesthepurposeandscopeofqualityactivitiesandresponsibilities,aswellasthepurpose,scope,organization,andrelationshipofthisdocumenttootherpertinentdocuments.
∙Section2,QualityManagementResponsibilities,explainstheresponsibilitiesforqualitymanagementontheCLASSProject.
∙Section3,QualityManagementApproach,definestheQMapproachtoassurecompliancewiththekeyconceptsofCLASSQM.
∙Section4,QualityManagementRecordsandReports,describestherecordsandreportspreparedandmaintainedbytheQualityFunction.
∙AppendixA,QMScheduleandMetrics,outlinestheproposedQMscheduleandmetricsreporttemplate.
∙AppendixB,DistributionofQualityResponsibilities,reflectsthedistributionofqualityeffortbetweentheQMOandCLASSprojectpersonnel.
∙AppendixCcontainsaglossaryofdefinitions.
∙AppendixDcontainsacronymsusedinthisdocument.
1.4ReferencesandRelatedDocuments
TheCLASSMasterProjectManagementPlan(MPMP)istheprimarydocumentdescribingthemanagementprocessesandstrategiesfortheoverallCLASSProject.TheMPMPdirectstheoverallprojectplanningfunctionanddefinestheorganization,resources,andmethodologyformeetingcustomerrequirements.
TheCLASSQMPsupplementstheMPMPanddocumentsthequalitymanagementfunction.Themanagementapproach,policies,andproceduresdescribedinthisplanarederivedfromCLASSprocessbaselinedocumentsandCSCFederalSectorpoliciesandprocedures.TheQMPwasdevelopedinaccordancewiththefollowingdocumentsandresourcesofwhichtheCLASSQMOfollows:
∙MasterProjectManagementPlan(MPMP),CLASS-1028-CLS-PLN-MPMP
∙CSDPCActivityPlan(AP),CLASS-1003-CLS-PLN-CSDPC
∙TMCActivityPlan(AP),CLASS-1073-CLS-PLN-TMCAP
∙ConfigurationManagementPlan(CMP),CLASS-1001-CLS-PLN-CM
∙SoftwareDevelopmentGuide(SDG),CLASS-1002-CLS-PRO-Guide
∙SoftwareDevelopmentMeasurementPlan(SDMP),CLASS-1054-CLAS-PLN-MA
∙CSCFEDCivilGroupQualityAssurancePolicy,SP611,Revision01,July2000
∙ComputerSciencesCorporation(CSC)Catalyst,QualityManagement,R4.0,Version1.0.2,2003
TheQMPreferstothefollowingsupportingdocuments:
∙ProcessAssuranceCycleprocedure,CLASS-1021-CLS-PRO-QM
∙QMOProcessAudits,CLASS-1023-CLS-PRO-QM
∙QMOProductReviews,CLASS-1019-CLS-PRO-QM
∙WaiverRequests,CLASS-1020-CLS-PRO-QM
∙CorrectiveandPreventiveActions,CLASS-1022-CLS-PRO-QM
∙PeerReviewsprocedure,CLASS-1018-CLS-PRO-QM
∙ConfigurationAuditsprocedure,CLASS-1025-CLS-PRO-CM
∙OperationalReadinessReviewprocedure,CLASS-1049-CLS-PRO-SIT
1.5DocumentMaintenance
TheQMPhasbeenreviewedandapprovedthroughindependentreviewbytheCSCFederalSector(FED)CivilGroup(CIV)QualityDirector,bytheCLASSProjectManagementTeam(CPMT),andisunderbaselinecontrol.DuringthecourseoftheCLASSproject,theQMorganizationwillcontinuallymakeimprovementstoitsinternalprocessestoensureaccuracy,thenreviewandupdatethisdocumentonayearlycycletoreflectprocessimprovements.Inthisway,theQMorganizationremainsefficientandresponsivetothecustomerandprojectqualityneedsandrequirements.AnychangestothisQMPwillbesubmittedtotheQMmanagerandthentotheCLASSProjectManagementTeam(CPMT)forauthorizationandapproval.
6Section2-QualityManagementResponsibilities
ThissectionidentifiestheQMresponsibilitiesandrelationshipsatalllevelsoftheCLASSproject,anddescribesthequalityresponsibilitiesoftheQMO,CLASSprojectmanagement,andtechnicalpersonnel.
2.1QualityObjectives
TheCLASSqualityobjectivessupportCLASSgoalsandobjectives,andestablishtheframeworkforplanningandperformingqualitymanagementactivitiesreflectedinprojectplans.TheCLASSqualityobjectivesareto:
∙Deliverproductsandservicesthatmeetcustomerneedsandbusinessobjectives
∙Deliverproductsthatarecompliantwithapplicablecontractandprojectrequirements
∙EmpowerCLASSpersonneltotakeresponsibilityforthequalityoftheirproductsandservices
∙Preventandresolveproblemsbyimplementingeffectiveworkprocesses
∙Promotecontinuousimprovementinworkprocessestoimprovequality,timeliness,andcost-effectiveness
∙ImprovetheeffectivenessofCLASSprocessesandtheirsupportingtools,techniques,standards,andprocedures
AllCLASSpersonnelareresponsibleforsupportingtheobjectiveswhileperformingassignedduties.TheCLASSQualityManagementOffice(QMO)isresponsibleformonitoringCLASSperformanceagainsttheobjectivesandfors