临时设施施工方案ENGLISH
04-上海-IIP-SHF-001
1.TemporaryFacilityPlan
NanjingChemicalIndustryGroupConstructionCompany
October21,2004
TableofContents
I.Introduction3
II.Reference4
III.ConstructionPreparation5
IV.WorkSequence5
V.ConstructionMethodandTechnicalSpecification5
VI.QualityManagement6
VII.HSEMANAGEMENT8
VIII.Managementofconstructionschedule12
I.Introduction
TemporaryfacilityconstructionasthefirststagetheCompanyentersintoIIPisofsignificance,forwhichthisPlanispreparedtoapplypermanentworkconstructionrequirementtothistemporaryfacility.
1、TemporaryFacilityconsistsofthefollowing:
A、ConstructionofaOfficeBuilding36M×15M,withthefollowingdetailedspecifications:
⑴、IndependentFoundationfooting400×400×250,14pieces.
⑵、ConcreteGroundFlooring,C15,THK120,withcushionofcrushedstone,THK80,and2EpoxyCoatingsonFloor
⑶、Superstructurewillbeoflightgaugedsteelstructure.Columnandrooftrusswillbefabricatedby20#C-ShapedSteel.Purlinwillbeof14#C-shapedSteel,withspanof15m(C-shapedSteel,2anti-corrosionundercoatingsand2topcoatings).Enclosuresystemwillbeofcladdingpanel(RoofPanelwillbe100MMTHK,ExternalWall75MM,InternalWallandoverhangingeave50MM),withsteelsheetingTHK0.3MM.(TCwillprovideTeamIIPdetailedDWGforapprovalpriortoconstruction.)
⑷、Falseceilingwillbeoflightgaugedsteelframework,withGypsumceilingpanel(Armstrong®)
⑸、Steelwindowwithplasticcoatingandsteelpaneldoor
B、ConstructionofaWarehouseBuilding42M×30M(2spans,15mforeachspan),withthefollowingdetailedspecifications:
1、IndependentFootings400×400×250,16piecesand700×700×250,8pieces.
2、ConcreteGroundFlooring,C15,THK100,withcushionofcrushedstone,THK80.
3、Superstructurewillbeoflightgaugedsteelstructure.Sidecolumnandrooftrusswillbefabricatedby20#C-shapedSteel.CentralColumnwillbefabricatedby25#C-shapedSteel.Purlinwillbeof14#C-shapedSteel,withspanof15m(C-shapedSteel,2anti-corrosionundercoatingsand2topcoatings).Enclosuresystemwillbeofsteelsheeting.Wallpurlinwillbeof12#C-shapedSteel(includingroofpanelandwallpanel.Overhangingeavespanelwillbe50MMTHK),withsteelsheetingTHK0.5MM.(TCwillprovideTeamIIPdetailedDWGforapprovalpriortoconstruction.)
4、Steelwindowwithplasticcoatingandsteelpaneldoor
C、ConstructionofaWorkshop(36×15m),withthefollowingspecifications:
⑴、IndependentFootings400×400×250,10pieces.
⑵、ConcreteGroundFlooring,C15,THK100,withcushionofcrushedstone,THK80.
⑶、Superstructurewillbeoflightgaugedsteelstructure.Columnandrooftrusswillbefabricatedby20#C-shapedSteel.Purlinwillbeof14#C-shapedSteel,withspanof15m(C-shapedSteel,2anti-corrosionundercoatingsand2topcoatings).Enclosuresystemwillbeofsteelsheeting.Wallpurlinwillbeof12#C-shapedSteel(includingroofpanelandwallpanel.Overhangingeavespanelwillbe50MMTHK),withsteelsheetingTHK0.5MM.(TCwillprovideTeamIIPdetailedDWGforapprovalpriortoconstruction.)
(4)Steelwindowwithplasticcoatingandsteelpaneldoor
D、PowerDistributionforTemporaryFacilities
TemporaryFacilitieswillbeprovidedwitha150KWdieselgenerator,aswellaspowerdistributionpanelforlightingpowerandconstructionpowerdistribution.Powerdistributionpanelwillbeproperlyearthed.Thefeederwillbeof3-phase-5-linesystem.Officebuildingwillbeprovidedwith2lightingpanels,forindoorlightingandpoweroutlet.Lightingfixturewillbebuilt-ingratingfluorescent,withgroupingcontrol.(Fordetails,seelightingpowerdistributionDiagraph).
II.Reference
GB50202-2002ConstructionAcceptanceCodeforBuilding’sFoundation
GB50203-2001ConstructionAcceptanceCodeforMasonryWork
GB50204-2001ConstructionAcceptanceCodeforConcreteStructureWork
GB50205-2001ConstructionAcceptanceCodeforSteelStructureWork
GB50209-2002ConstructionAcceptanceCodeforBuilding’sFlooring
GB50300-2001BuildingConstructionUniformAcceptanceCode
ConstructionDWGforTemporaryFacility
III.ConstructionPreparation
TCwill,asperTEAMIIP’sregulation,provideafulltimeexperiencedandqualifiedsafetysupervisorforevery30workers,forpropersafetymanagement.
Constructionequipmentandtoolswillbepreparedincluding:
temporarypowersupplyanddistribution,crane,welder,liftingcageandotherappropriateandqualifiedfacilities,toolsanddevices.Alltoolsandequipmentshall,beforebroughtintosite,befullyinspected.Detailedrecordshallbeestablishedforthesequalifiedequipment.ConstructiontoolsandequipmentshallbeinspectedandapprovedbyattachingcertificatetagbyTeamIIPbeforemovedintosite.Equipmentoperatorsshallreceivetrainingandfamiliarizeequipmentperformance,operationandsafetytechnology.OperatorsshallhaveCertificateforOperation(orCopy)atanytime.
IV.WorkSequence
TemporaryFacilityconstructionwillbedividedintothefollowing2stages:
Stageone:
OfficeBuilding.FoundationandFlooringwillbefromOct18,2004toOct26,2004.StructuralsteelprefabricationwillbefromOct18,2004toOct28,2004.SteelerectionisscheduledtostartonOct31,2004andfinishonNov8,2004.
Stagetwo:
WorkshopandWarehouse.FoundationandFlooringwillbefromNov6,2004toNov20,2004.StructuralsteelprefabricationwillbefromNov8,2004toNov18,2004.SteelerectionisscheduledtostartonNov15,2004andfinishonNov29,2004.
V.ConstructionMethodandTechnicalSpecification
SurveytheareathatTeamIIPgrantedtoestablishthetemporaryfacilityandmakesitepreparationbybulldozer.Steelpipestakewillbesetupforevery2matperipheralforfencingestablishment.
Forlimitedconcretework,readymixedconcretewillbecumbersometouse.Anappropriateareawillbeselectedformanualconcretemixing.Readymixedconcrete,approvedbyTeamIIP,willbeusedforlaterlargeconcretepouring.
WorkProcessforGroundFlooringandFoundation:
FieldCompacting——FormErection——ConcretePouring——ConcreteCuring
WorkProcessforSteelStructureErection:
SteelColumnErection——PurlinandBeamErection——RoofingSystemErection——WallSystemErection——RainwaterPipeandDoor&WindowErection——EntireInspection——Acceptance——Cleanup
Forthesakeofprogress,A25tonnageratedcranewillbeusedformaterialoffloading,steelassemblyandlifting.
Scaffoldingshallbeproperlyestablishedforanyerectionworkatelevationover2m.Steelfittershallproperlyuseharnessbyattachingthehooktoafirmandreliableobject.
VI.QualityManagement
QualityRequirement
A.Makepreparationsforconstructioninaccordancewithrequirements
(1)Givesafetyandtechnologyorientationbeforeconstruction;
(2)ProposequalityinspectionpointsandsubmittoIIPandownertoreviewandapprove.Reinforcethemanagementofspecialdisciplineandinspectthequalitycontrolpointsduringtheconstructionpreparationstage.
B.Controlonthecourseofconstruction
(1)Reinforcethemanagementofmaterial,semi-finishandequipments;disqualifiedmaterialandequipmentsshallnotenterthesite;materialatsiteshallbeclassifiedbytaggingandstackedinorder.
(2).Strengthentheorganizationandcoordinationatsiteandensuretheinstructionisimplementedimmediately.
(3).Reinforcesupervisionandinspectionoverconstructionteamstoensurequalifiedworkisdoneforthesakeofprojectquality.
(4).Reinforcethemanagementandcontrolofworksequencetoimplementqualitypre-control.Toproceedtosubsequentworksequenceafterpreviousworkiscompleted.Performstrictlythree-levelABCqualitycontrolpointstoconfirminspectionworkandensurejoint-inspectionprogresssmoothly.
(5).Siteenvironmentinaccordancewithrequirements.
(6).Filloutqualityrecordsinaccordancewithrelevantregulationsandcriterionandkeepthemexactandclear,qualityrecordsshallbefilledbyinspectorandreviewedbyqualityengineer.
(7).Themanagementofsiteequipmentsandmeasurementequipmentsshallbeimplementedasperrelevantprovisions.
C.Thequalitycontrolofpostconstruction
Inspectcarefullyandreviewconstructionworkbeforethecompletionandensureproperhandover.
D.Inspectionandtest
1.Inspectandtestallworkhavingbeendoneonsiteandoffsite,includingmaterial.
2.Concretetestwillbeperformedbyqualifiedcivillab,aswellasqualifiedNDEinstitute.
3.OnlyInspectionInstitutewithpertinentqualificationcertificateshallassumespecialtest.
4.Supervisionandmeasurementofprocedurequalitycontrolpoints:
procedurequalitycontrolpointsincludingself-inspection,disciplineinspection,coveredworkinspection,procedurehandoverinspectionandjointinspection,etc.eachinspectionresultshallbefilledintheinspectionrecord,priortocoveredworkandaftertheHoldPoint(A),WitnessPoint(B)programfinished,Companymustreviewandapprovetosignature,thenmakecoveredworkandshifttothenextprocedure.Givenoticetothecontractorpriortocountercheck,theaheadnoticetimeseethefollowingchart:
Concretecastingoneday
Buildingsacceptanceinspectionstwodays
BoltTighteningFourhours
Othertests/inspectionsTwohours
E.QUALITYRECORDS
CheckandhandoverconstructionqualityrecordinaccordancewithhandoverrecordmanagementrequirementstipulatedbyIIP.
Priortoconstruction,contractorshallprepareasetofturnoverforms,reviewedbyIIP,toconfirmtheformatofturnoverrecordformsandfilloutthemaccordingtoascertainedturnoverrecord,ifchangeable,nottouse