PPP养老模式复习课程Word文档格式.docx
《PPP养老模式复习课程Word文档格式.docx》由会员分享,可在线阅读,更多相关《PPP养老模式复习课程Word文档格式.docx(9页珍藏版)》请在冰点文库上搜索。
WAISAHMADBAHEEN
2017280350
Contents
1.Introduction
Apublic-privatepartnershipisacooperativearrangementbetweentwoormorepublicandprivatesectors,typicallyofalong-termnature(GraemeA.Hodge).PPPsofteninvolveacontractbetweenapublicsectorauthorityandaprivateparty,inwhichtheprivatepartyprovidesapublicserviceorprojectandassumessubstantialfinancial,technicalandoperationalriskintheproject.
Public-privatepartnership(PPPs)areanincreasinglycommonmodelfordeliveringinfrastructureprojectsglobally(Hovy).OneofthekeymotivationsforgovernmentstoprocureanddeliverInfrastructureprojectviaPPPmodelsistheassumptionthatPPPsdelivergreatervalueformoney(VFM)thanconventionaldeliverymethods.However,duetothelongconcessionperiodandlargeamountofinvestment,therisksassociatedwithPPPprojectsshouldnotbeunderestimated.Generally,riskmanagementincludes:
riskidentification,riskassessmentandriskresponses(PMBOK,2004).AllocatingrisksinPPPs,however,isinherentlychallenging(Hovy).Risktransfertotheprivatesectorcomesataprice,andtransferringrisksthatthepublicagencyisbetterabletomanageislikelytoerodeVFM.
Chinaisfacingarapidgrowthofpeoplewhoseageis60yearsorabove,whichispredictedtodoubleoverthenextdecade.Bythe2014thenumberofelderlypeoplewhoseagewas60orabovehadreached210million.Andisprojectedtoexceed400millionoverthenextdecade,which
Figure1PercentageofOlderPopulation
isanincreaseof28.7percent,from15.5percentasofyear2014.MorethanhalfofChineseelderlyagepeoplearelivingontheirown.Andthispercentageisevenhigherinthelargeandmediumcities.Accordingtoaresearchresult,about70percentofolderadultsarelivingaloneorwithaspouseonlyThustofacethecurrentrapidgrowthofagingprobleminChina,governmenthasfocusedonestablishingsocialinfrastructuresandimprovinghealthcareandwell-beingofpeople.Apossiblewayofcombatingtheagingproblemisseeminglyestablishingapublic-privatepartnershipprojectforaginginplace.
Traditionally,Chineseolderadultsremainedathome,caredbyfamilymembersratherthanbylong-termcareinstitutions.Duetothe“emptynest”problem,anincreasingnumberofolderadultswillbeinneedofexternalcareservices,buttheavailabilityofaffordable,publicnursinghomesislimiteddespitethegovernment’scontinuedeffortstoexpandthecapacity.(Luo).
Public-privatepartnershipventureisaninnovativeAginginPlacemodelfortheelderlyofferingcarecoordinationandhealthcareservicestoolderadultsresidinginspeciallydesignedseniorapartments,otherseniorprivateorpubliccongregatehousing,orintheirownhomesinthecommunity.Aginginplaceisamuchhealthierapproachascomparewithlong-termcaredeliverytrajectorythatforcesafrailolderpersontomovefromonesettingtoanotherasneedschangeandresultsinmentalandphysicaldeterioration((Karen).
Aquestionarisesastohowgovernmentcanbestdrivedesirableoutcomes,whileenduringthattheprivatesectoracceptsanappropriatelevelofrelatedriskandisgivenscopetoinnovateindesigningtheinfrastructure.AndashowgovernmentcanensureasuccessfuldeliveryofsuchlongtermAginginPlaceproject(fosterinfrastructure,2012).ForAginginPlacetobesuccessfulolderadultsmustliveinanenvironmentsupportiveofindependence,andcaremustbecoordinatedthroughoutthehealthcaresystem(Karen).
2.Background:
AginginPlaceinChina
Ifinterpretedintermsofrelaxationofrules,someofthepensionprogramscurrentlyonthemarketareactuallyproductsofconcertedeffortsbetweenthegovernmentandenterprisesandcanbecalledPPPinabroadsense.
AsofJune30th2016,therewere239nationalpensionPPPproject,accountingfor2.57%ofthe9,285PPPprojectsnationwide.ThenumberofPPPprojectsaimedatmedicalandhealth(433)incomparetomostlyusedPPPdeliveryprojectssuchasengineering(3241),transportation(1132),areadevelopment(554)andotherfields,arerelativelysmall.
Figure2PPPProjectsPortion
AsofJune30th2016,thetotalinvestmentinpensionprojectsnationwidereached141.1billionyuan,accountingfor1.33%ofthetotalinvestmentinthecountry’sPPPprojectsof10.6trillionyuan.
AsofJune30th2016,ShandongandGuizhouprovinceshavethelargestnumberofpensionprogramsthatusethePPPmodel,46and40respectively.FollowedbyHenan(21),Sichuan(19)andXinjiang(19),respectively.Oftheeightprovincesandmunicipalitiesthataredirectlyunderthecentralgovernment,therearenoPPPpensionprogramsestablishedinthesecities,includingShanghai.
AsofJune30th2016,ofthe239pensionPPPprojectsinthecountry,thenumberofprojectsinvestedinretirementstandat137(57%)whichislargerincomparetoprojects,suchaselderlyapartmentprojects50(21%),healthcareprojects48(20%)andotherfieldsprojects4(2%),respectively.
Figure3NumberofPesionPPPProjects
Asoneofthefinancialinstrumentsusedbythegovernmenttoboostthedevelopmentofoldindustries,thePPPmodelhasdrawnmuchattentionduetothehighdegreeofgovernmentsupport,thelong-termstabilizationofthemarketdemandtherelativelytransparentchargingpricingmechanism.However,theroleofPPPmodelinthefieldofAginginPlacehasnotyetbeenbroughtintofullplay.Governmentleverageneedstobeincreasedtofacilitatetheeffectiveparticipationofdiversesocialcapital.
3.IdentifyingriskinPPPprojects
Riskmanagementbeginswithriskidentificationandclassification(PMBOK,2004).Hence,it’simportanttoidentifytheriskinPPPprojects,andtherisksallocatedwithAginginPlaceproject.InaPPP,theprivatesectorpartnerhasanincentivetocompleteconstructionon,oraheadof,timeandprovidehigh-qualityservices,aspaymentsdonottypicallycommenceuntiltheassethasbeenbuiltandanagreedlevelofserviceisbeingprovided.Onavalue-weightedaveragebasis,PPPprojectsaredelivered3%aheadofschedulecomparedto24%behindschedulefornon-PPPprojects.Asshownbelow:
Figure4DeliveryAdvantage
WithreferencetothecommonlyacceptedacademicanalysismethodsandcombiningwiththecharacteristicsoftheAginginPlaceprojects,theriskofPPPprojectinAginginPlacearedividedintothreelevels:
macrorisk,mid-rangerisk,andmicrorisk.
i.MacroRisk
Macroriskistheriskthatcomesfromtheenvironmentinfluencewheretheprojectislocated.Specificallyreferstothecountry,industryandnaturalrisks,suchaspoliticalandlegalconditions,economicconditions,socialconditions,andclimateconditions.Essentially,theserisksstemfromtheriskeventsthatoccuroutsidetheprojectssystemboundaries,impactingtheprojectitselfandthepost-operationaloutputsacrosstheprojectssystemboundaries.PPPprojectsinAginginPlaceshouldalsotakeintoaccounttherelevantlegalpolicies,socialconcepts,marketdemandandotherriskfactors.Macro-riskisdividedintofivemajorcategories:
politics,economy,law,societyandnaturalenvironment.Asshownbelow:
Figure5Macro-riskFactorsinPPPAginginPlaceprojects
ii.Mid-rangerisk
Themid-rangeriskarisesfromtheprojectitself,andtheriskeventsandtheirconsequencesoccurwithintheproject’ssystemboundaries,reflectingtheimplementationofthePPPproject.Themid-rangeriskaredividedintofourdifferentfactors:
finance,design,implementation,andlogistic.Asshownbelow:
Figure6Mid-ragerisksinPPPAginginPlaceprojects
iii.Micro-Risk
Themicro-riskisrelatedtoeachparticipantoftheprojectandistheriskcausedbythedevelopmentandchangeofvarioustypesofcontractualrelationshipsbetweenvariousstakeholdersintheprocessofprocessofprojectimplementation,anditalsobelongstoendogenousrisk.Micro-risksinthisarticleiscarriedoutfromtheaspectofcooperationamongpartnersandthird-partyresponsibilities.Themostimportantriskarisesfromtheconflictofinterestbetweengovernment,publicsectorandthesocialcapitalparticipants.Thepublicsectorinterestsaremainlyembodiedintherealizationofsocialbenefits.Theactionsofsocialcapitalparticipantsarecompletelyfreeandprofit-driven.Conflictsofinterestareinevitable,resultinginariskperiodthataffectstheoutputoftheproject.Therelationshipisshownbelow:
Figure7Micro-RisksinPPPAginginPlaceProjects
4.AllocatingRiskinPPPAginginPlaceProject
Thegoalofprojectsharingistomaximizethesatisfactionofpublicandprivatesectoroftheplansothattheresultofriskallocationwouldreducetheprobabilityofriskoccurrenceandriskmanagementcost,andtomakePPPprojectattractivetoallparties.Thisrequiresthattheriskappetiteofdifferentrisk-bearingentitiesshouldbeestablishedandacorrespondingrisk-sharingmechanismshouldbeestablishedsothattheprojectcanachieveawin-winsituation.
Consideringhugeinvestment,longconstructionandoperationperiods,andmanyuncertaintiesintheconcessioncouldhappen,inadditionthecomplicatedrelationshipamongtherisk-bearingentities,theriskshouldbeallocatedtothepartybestabletomanagethem.Inotherwords,thepartythatisbestabletounderstandarisk,controllikelihoodoftheriskoccurringand/orminimizetheimpactoftheriskshouldalsoberesponsibleformanagingit(PaluineHovy,2015).
1.
a)Government
ThepoliticalenvironmentriskandlegalriskfacedbypensionPPPprojectsmainlycomefromthes