Communications
1.9
ProvisionofConstructionDocuments
1.10
Employer'
sUseofContractor'
sDocuments
1.11
Contractor'
sUseofEmployer'
1.12
ConfidentialDetails
1.13
CompliancewithStatutes,RegulationsandLaws
1.14
JointandSeveralLiability
2
2.1
THEEMPLOYER
GeneralObligations
2.2
AccesstoandPossessionoftheSite
2.3
Permits,LicensesorApprovals
2.4
sEntitlementtoTerminate
3
3.1
THEEMPLOYER'
SREPRESENTATIVE
sRepresentative'
sDutiesandAuthority
3.2
RequirementsforEmployer'
sRepresentative
3.3
sAuthoritytoDelegate
3.4
sInstructions
3.5
sRepresentativetoAttemptAgreement
4
4.1
THECONTRACTOR
4.2
PerformanceSecurity
4.3
4.4
Co-ordinationoftheWorks
4.5
Subcontractors
4.6
AssignmentofSubcontractor'
sObligations
4.7
SettingOut
4.8
QualityAssurance
4.9
SiteData
4.10
MattersAffectingtheExecutionoftheWorks
4.11
UnforeseeableSub-SurfaceConditions
4.12
AccessRoute
4.13
RightsofWayandFacilities
5/58
4.14Programme
4.15ProgressReports
4.16Contractor'
sEquipment
4.17SafetyPrecautions
4.18ProtectionoftheEnvironment
4.19Electricity,WaterandGas
4.20EmployerSuppliedMachineryandMaterials
4.21ClearanceofSite
4.22SecurityoftheSite
4.23Contractor'
sOperationsonSite
4.24Fossils
5DESIGN
5.1GeneralObligations
5.2ConstructionDocuments
5.3Contractor'
sUndertaking
5.4TechnicalStandardsandRegulations
5.5Samples
5.6As-BuiltDrawings
5.7OperationandMaintenanceManuals
5.8ErrorbyContractor
5.9PatentRights
6STAFFANDLABOUR
6.1EngagementofStaffandLabour
6.2RatesofWagesandConditionsofLabour
6.3PersonsintheServiceofOthers
6.4LabourLaws
6.5WorkingHours
6.6FacilitiesforStaffandLabour
6.7HealthandSafety
6.8Contractor'
sSuperintendence
6.9Contractor’sPersonnel
6.10DisorderlyConduct
7PLANT,MATERIALSANDWORKMANSHIP
7.1MannerofExecution
7.2DeliverytoSite
7.3Inspection
7.4Testing
7.5Rejection
7.6OwnershipofPlantandMaterials
8COMMENCEMENT,DELAYSANDSUSPENSION
8.1CommencementofWorks
8.2TimeforCompletion
8.3ExtensionofTimeforCompletion
8.4DelaysCausedbyAuthorities
8.5RateofProgress
8.6LiquidatedDamagesforDelay
8.7SuspensionofWork
8.8ConsequencesofSuspension
8.9PaymentforPlantandMaterialsinEventofSuspension
8.10ProlongedSuspension
8.11ResumptionofWork
9TESTSONCOMPLETION
9.1Contractor'
9.2DelayedTests
9.3Retesting
9.4FailuretoPassTestsonCompletion
10EMPLOYER'
STAKINGOVER
10.1Taking-overCertificate
10.2UsesbytheEmployer
10.3InterferencewithTestsonCompletion
11TESTSAFTERCOMPLETION
11.1Employer'
11.2DelayedTests
11.3Retesting
11.4FailuretoPassTestsafterCompletion
12DEFECTSLIABILITY
12.1CompletionofOutstandingWorkandRemedyingDefects
12.2CostofRemedyingDefects
12.3ExtensionofContractPeriod
12.4FailuretoRemedyDefects
12.5RemovalofDefectiveWork
12.6FurtherTests
12.7RightofAccess
12.8ContractortoSearch
12.9PerformanceCertificate
12.10UnfulfilledObligations
13CONTRACTPRICEANDPAYMENT
13.1TheContractPrice
13.2AdvancePayments
13.3ApplicationforInterimPaymentCertificates
13.4ScheduleofPayments
13.5PlantandMaterialsforthePermanentWorks
13.6IssueofInterimPaymentCertificates
13.7Payment
13.8DelayedPayment
13.9Paymentof'
RetentionMoney
13.10StatementatCompletion
13.11ApplicationforFinalPaymentCertificate
13.12Discharge
13.13IssueofFinalPaymentCertificate
13.14CessationofEmployer'
sLiability
13.15CalculationofPaymentsinForeignCurrency
13.16ChangesinLegislation
14VARIATIONS
14.1RighttoVary
14.2ValueEngineering
14.3VariationProcedure
14.4PaymentinApplicableCurrencies
14.5ProvisionalSums
15DEFAULTOFCONTRACTOR
15.1NoticetoCorrect
15.2Termination
15.3ValuationatDateofTermination
15.4PaymentafterTermination
15.5Bribes
16DEFAULTOFEMPLOYER
16.1Contractor'
sEntitlementtoSuspendWork
16.2Termination
16.3CessationofWorkandRemovalofContractor'
16.4PaymentonTermination
17RISKANDRESPONSIBILITY
17.1Indemnity
17.2Contractor'
sCareoftheWorks
17.3Employer'
sRisks
17.4ConsequencesofEmployer'
17.5Contractor'
17.6LimitationofLiability
18INSURANCE
18.1InsuranceforDesign
18.2InsuranceforWorksandContractor'
18.3InsuranceagainstInjurytoPersonsandDamagetoProperty
18.4InsuranceforWorkers
18.5GeneralRequirementsforInsurances
19FORCEMAJEURE
19.1DefinitionofForceMajeure
19.2EffectofForceMajeureEvent
19.3Contractor'
sResponsibility
19.4Employer'
19.5PaymenttoContractor
19.6OptionalTermination,PaymentandRelease
19.7ReleasesfromPerformanceundertheLaw
20CLAIMS,DISPUTESANDARBITRATION
20.1ProcedureforClaims
20.2PaymentofClaims
20.3DisputeAdjudicationBoard
20.4ProcedureforObtainingDisputeAdjudicationBoard'
sDecision
20.5AmicableSettlement
20.6Arbitration
20.7FailuretoComplywithDisputeAdjudicationBoard'
20.8ExpiryofDisputeAdjudicationBoard'
sAppointment
PARTI-GENERALCONDITIONS
1TheContract
Definitions 1.1IntheContract(asdefinedbelow)thewordsandexpressionsdefinedblowshallhavethemeaningsassignedtothem,exceptwherethecontextrequires,otherwise:
1.1.1Documents
1.1.1.1 “Contract”meanstheseConditionsofContract(PartsIandII),theEmployer'
sRequirements,theTender,theContractor'
sProposal,theSchedules,theLetterofAcceptance,theContractAgreement(ifcompleted)andsuchfurtherdocumentsasmaybeexpresslyincorporatedintheLetterofAcceptanceorContractAgreement(ifcompleted).
1.1.1.2“EmployerRequirements”meansthedescriptionofthescope,standard,designcriteria(ifany)andprogrammeofwork,asincludedintheContract,andanyalterationsandmodificationstheretoinaccordancewiththeContract.
1.1.1.3“Tender”meanstheContractor'
spricedoffertotheEmployerfortheWorks,asacceptedbytheLetterofAcceptance.
1.1.1.4 “AppendixtoTender”,meansthecompletedappendixcomprisedintheTender.
1.1.1.5 “Contractor’sProposal”meansthepreliminarydesignsubmittedwiththeTender,asincludedintheContract.
1.1.1.6 “Schedules”meanstheinformationanddatasubmittedwiththeTender,asincludedintheContract.
1.1.1.7 “ScheduleofPayments”meanstheScheduledesignatedassuch(ifany),referredtoinSub-Clause13.4.
1.1.1.8 “LetterofAcceptance”meanstheformalacceptancebytheEmployeroftheTender.
8/58
1.1.1.9“ContractAgreement”meansthecontractagreement(ifany)referredtoinSub-Clause1.5.
1.1.2Persons
1.1.2.1“Employer”meansthepersonnamedassuchintheAppendixtoTenderandthelegalsuccessorsintitletosuchperson,butnot(exceptwiththecontentoftheContractor)anyassigneeofsuchperson.
1.1.2.2“Contractor”meansthepersonwhoseTenderhasbeenacceptedbytheEmployerandthelegalsuccessorsintitletosuchperson,butnot(exceptwiththecontentoftheEmployer)anyassigneeofsuchperson.
1.1.2.3 “Employer’sRepresentative”meansthepersonappointedbytheEmployertoactasEmployer’sRepresentativeforthepurposesoftheContractandnamedassuchintheAppendixtoTender,orotherpersonappointedfromtimetotimebytheEmployerandnotifiedassuchtotheContractor.
1.1.2.4“Contractor’sRepresentative”meanstheperson(ifany)namedassuchintheContractorotherpersonappointedfromtimetotimebytheContractorunderSub-Clause4.3.
1.1.2.5“Subcontractor”meansanypersonnamedintheContractasasubcontractor,manufacturerorsupplierforapartoftheWorksoranypersontowhomapartoftheWorkshasbeensubcontractedinaccordancewithSub-Clause4.5,andthelegalsuccessorsintitletosuchperson,butnotanyassigneeofsuchperson.
1.1.2.6“DisputeAdjudicationBoard”meansthepersonorpersonsnamedassuchintheContractorotherpersonorpersonsappointedfromtimetotimeunderSub-Clause20.3.
1.1.3Dates,TimesandPeriods
1.1.3.1“BaseDate”meansthedate28dayspriortothelatestdateforsubmissionoftheTenderforacceptancebytheEmployer.(Latestdate)
1.1.3.2“EffectiveDate”meansthedateonwhichtheContractenteredintolegalforceandeffect.
1.1.3.3“CommencementDate”meansthedateonwhichtheContractorreceivesthenoticetocommenceissuedbytheEmployer’sRepresentativeunderSub-Clause8.1.
1.1.3.4“TimeforCompletion”meansthetimeforcompletingtheWorksoraSection(asthecasemaybe),andpassingtheTestsonCompletion,asstatedintheAppendixtoTender(orasextendedunderS