地下GRP管道施工方案
MethodStatementUndergroundGRP
PipingInstallationWorks
Title:
UndergroundGRPPipingInstallationProcedure
TCCPreparedBy
Name:
Position:
Signature:
Date:
DAELIMApproval
Name:
Position:
Signature:
Date:
ApprovedByClient
Name:
Position:
Signature:
Date:
Rev.0
ThisDocumentisthepropertyofTCC.Issuedto,andusedbyothersneedsthewrittenapprovaloftheTCCQualityManager.
CONTENTS
1.0Purpose
2.0Scope
3.0Reference
4.0Responsibilities
5.0EquipmentsandTools
6.0LaminationProcessSequence
7.0BondingMaterials
8.0ReceivingHandlingandStoringofPipe
9.0ArrangePipeinTrench
10.0JointLaminateProcedure
11.0QualityRequirements
12.0SafetyPrecaution
13.0Attachments
1.Purpose
ThismethodstatementistoguidebuttjointwraplaminationworkofU/GGRPpipingsystemintheArabianChlorVinylProject.
2.Scope
ThisMethodStatementcoversthefieldlaminationjointsinstallationmethodofundergroundGRPpiping.
ThisprocedureisapplicabletoallU/GGRPpipediameters.
RelateddataofU/GpipingGRPpartisasfollowing:
Systemdescription
Materialclass
Diameterrange
ConnectionMethod
WW
DGAANA
4”,6”,8”,10”,12”,20
Butt&wrapjointlamination
ACW
DGAANA
4”
Butt&wrapjointlamination
PCS
DGAANA
4”
Butt&wrapjointlamination
3.Reference
1Thedrawingof
080036-AA-DA-100201~400207U/GCompositeDWG
2Specification:
080036-AA-SG-007SpecificationforUndergroundPiping&SurfaceDrainage
080036-XH-SG-003Specificationforpipingconstruction
080036-XZ-SG-001SpecificationforPipingDesign
080036-QZ-PL-001ProjectQualityPlan
080036-XH-SG-006SpecificationforIdentificationofPipingMaterial
080036-XH-SL-005SpecificationforPipingMaterial
AMIANTITdocument:
FieldButt&WrapJointProcedureForGRP/FRPPiping
InstallationandHandlingInstructionsForRigidJointPipe
FieldLaminationProcesssheet
4.Responsibilities
4.1GRPManager
InchargeofalltheactivityduringtheGRPpipeconstruction.Mainlyinvolvethesafety,techniqueandqualityproblemsduringtheconstruction,preparingandcarryingouttheconstructionschedules.
4.2QCSupervisor
InchargeofskilltrainingforallthepersonnelwhowillengagetheGRPpipingwork,analyzingthesafetyissuesandprovidingprecautions.Applyingforworkpermits
4.3QCInspector
CompilingQCprecautions,solvingtheQCissuesduringGRPpipingconstruction,takingpartinqualityinspectionandacceptanceandtakingthemajorresponsibilitiesforthequalityoftheGRPpiping.
5.EquipmentsandTools
ThebelowitemsareusedfortheGRPPipinghandlingandConstruction:
☻Boomtrucks,trailersandcranes,shackles,slingsbelts,supports,crosstieforpipingtransportation
☻Anglegrinder,diamondblades,diegrinderandflapwheelsforcuttingandgrinding
☻Squarebasin,paintrollers,brushesandSteelgroovedrollersforlamination
☻HotairdryerandDigitalinfraredthermometerforcuring(ifrequired)
☻MeasuringtapeandBarcolhardnesstesterforlaminationtest.
☻Mobiledrumcradle,spilldecks,pluglesstapandsteelgantriesforresinstore.
☻Glasscuttingtable,rollingtubes,knives,bladesandscissorsforglassprepare.
☻Buckets,Liquidstoragecontainers,platformbalance,stirrer,spilltraysforresinmeasureandmixture.
☻Dispensingbottles(orsimilartools)andchemicalagentbottlesformeasuringandbringingcatalysttosite.
☻Brassbristles,plasticbrush,cleaningbasin,dusterclothfortoolscleaning.
6.laminationProcessSequence
7.BondingMaterials
Usedcomponents
RESIN:
EpoxyvinylesterresinsuppliedfromAmiantit,andtobemixeditwithcatalyst.
CATALYST:
Methylethylketoneperoxide.
Mat&WOVENROVING:
glassreinforcementforjointstructure.
BONDINGMATERIALSSTORAGEandUSAGE:
DetailsseeattachmentA:
FieldButt&WrapJointProcedurePage4to5.
Thelocationofresin,W-Fluid,catalyst&glassreinforcementcontainerasshowinfigure7-1
Figure7-1
Storageoutlineofchemicalcontainerdetailsseeattachment-F:
InteriorlayoutforAmiantitResin&Catalyst
8.Receiving,HandlingandStoringofPipe
DetailsseeattachmentB:
InstallationandHandlingInstructionsForRigidJointPipePage2to4.
InspectingPipe
●AllpipesreceivingatsiteshallbeinspectedaccordingtoSpecificationforPipingMaterial.
●Brokenpipebundles,crushedfittingsboxesshouldbecheckedcarefully,scratchedandgougedandpipewithcrushedorsplitendsarenotallowedtouse,damageclaimsproceduresmustbeinitiatedpriortoacceptingtheshipment.
●Donotdisposeofanydamageditems.Ifanyimperfectionordamageisfound,immediatelysegregatetheaffectedpipesandcontactDealim.Donotusepipethatappearsdamagedordefective.
HandlingPipe
●Pipes,fittingsandprefabricatedparts(spools)havetobetransportedbysuitabletrucks.Thesetrucksmusthaveflatfloors.Checkandremoveanyprojectionsornailsetc.beforeeachload.Materialsmustbesecuredforexamplebyusingwedgesandwoodensupports.Thesesupportsmusthaveaminimumwidthof10cm,avoidingsharpedges.Thesupportdistancesmustnotexceed2.5m.
●Donotliftthepipebypassingaropethroughthesectionendtoend.
●Anypartofthetruckhastobeprotectedbywoodorrubberwhereverincontactwiththeproducts.Ifpipesarehandledbyaforklifter,theforksmustbecoveredwithrubberorplastic.
●Forworkonthepipe,suchascutting,preparingends,orcleaning,two-pointsupportisrecommendedfor20-footlengths,andthree-pointsupportfor40-footlengths.Supportwoodshouldbeensurednonails.
●Thebestwayforfittingstobetransportedisincratesorontopallets.Directcontactbetweenproductsduringtransportmustbeavoided.
PipeStorage
●Donotlaythepipesdirectlyontheground,railsorconcretefloors.
●Ensuresuitablesupportsareusedforexamplewoodenbeams,measuring10x5cm.Toavoiddamagetomachinedpipeends,stackingshouldbeundertakenwithcare.Themachinedendsmustbeprotectedforexamplebypolyethylenecoveredstrawmatsorpolyethylenenetting.
●Iftheproductisstackedtoohighforlongstorageperiods(6-12months).Itisrecommendedthattheproductisstoredundertarpaulinsor(white)polyethylenesheeting.
●Pipestacksshouldhavesidesupportsorblockstopreventrollingorslippingofthestackduringstormyweather.Aleveled,softearthsurfacefreeofrocksandotherhardorsharpobjectsisrecommended.
9.ArrangePipeinTrench
PrepareandassemblepipeandjointsinaccordancewiththeISOdrawing,usingspecialcaretokeepjointsurfacecleananddry.
Positionpipeontimbersacrossditchasshowninfigure-1.Blockintopositiontoholdalignmentandpreventlateralmovement.
Jointthepipesufficientlyinadvanceofthepipeloweringoperationsothatnomovementofthepipewilltakeplaceatlocationwherejointsarebeingcured.Anyvibrationormovementofuncuredorpartiallycuredjointswillincreasetheriskofjointfailures.
Shouldbemakesurethedepthofthetrenchbeforelowingthepipe.Figure-1
Withpowerequipmentormanpower,raisethepipeslightlytoslidethetimbersupportfromunderthepipe.Lowerthepipeintothetrench.Donotdroporlowersuddenly.Repeattheaboveoperationateachsupport.Useropeorwebbedslingforliftingpipe.Ifmanpowerisused,itissuggestedthattwomenbeusedforlifting6-inchpipe,andfourmenandmuchmorebeusedforthe8-inchandbiggerpipe.
10.JointlaminationProcedure
10.1Cutting
Thisinitialstepshallbeapplicableonlyifapipeendneedstobecutandreplaced,orapipelengthrequiresfieldadjustment.Markthepipesectiontobecutusingawrap-aroundandawhitemarker.
Cutthepipeusingahacksaworadiamondcuttingdisc,makesurethatapropersquarecuthasbeenmade.Ensurethatcutendsremainwithinthetolerancesasshowintable10.1.
Table10.1:
Maximumtoleranceonsquareofcuttedpipeend
PipeSizeRange
Tolerance
(mm)
(mm)
(inch)
25-100
1-4
1.5
150-400
6-16
3.0
10.2Grinding
Grindingandcleanningthetotalexternalsurface.MakesurethatthepipeendsaregrindedaswellastherequiredlengthasattachmentC:
Fieldlaminationprocesssheet.
Startthelaminationofthefittedsectionswithintwohoursaftersanding;re-sandingofthelaminationareashallberequiredifthewaitingperiodexceedstwohours.
Bondingsurfacesmustbedryandcleanbeforesanding.Useflapperwheelsanderswithasmalldrillingmachine(1700-2000rpm)oremeryclothwithagridof60.Sandedsurfacesmusthaveadull,freshfinish,notapolishedlook.Removeanypossibledewbyslightlyheatingthepipeendsbyahotairdryer.
OtherdetailsseeattachmentA:
FieldButt&WrapJointProcedurePage7.
10.3Fittingup
1Checkthealignmentandfixingthepipeendsascloseaspossible,thenpreparetheputty.
2Applytheputtywithaputtyknifefillingallthegap;
3Afterthefillingofthegap,theputtyshallpolymerize,withoutmovingandbumpingthepieces.
4Oncecompletedthehardeningoftheputty,grindtheoutsideofthepipejointandcleanwithairblowandcleandustercloth.
Note:
Thegapshouldnotexceedthe5mmorasperrecommendedbyPipemanufactureratanycase.
10.4FieldJointKitsPrepare
DetailsseeattachmentA:
FieldButt&WrapJointProcedurePage8FIELDJOINTKITS.
Eachjointkitshouldbestoredinacloseroomtoavoiddust,damp&directsunlight,andshouldbestoredinadryareaandlessthan65%humidityinordertoavoidsurfacecondensationwhenusedinwarmerconditionsoutside.
10.5Laminationonthepipejoint
DetailsseeattachmentA:
FieldButt&WrapJointP