PhaseIICFDoilfieldWGPAsystempreparationsRev02
Kerr-McGeeChinaPetroleumLtd.
CFD11-1/2FieldDevelopment
DocumentTitle
PhaseII–WGPAPreparationForFirstOil
DocumentNo.
CFD11-OP-PR-002
02
06/23/2004
IssuedforApproval
TangLiang
KeironThomson
01
05/27/2004
IssuedforComment
TangLiang
KeironThomson
Rev.
Date
Description
Originator
Checked
Approved
REVISIONS
Kerr-McGeeChinaPetroleumLtd
CFD11-1/2FieldDevelopment
CFD11-1/2FieldStart–UpProcedures
CFD11-OP-PR-002
PhaseII-WGPAPreparationfor1stOil
CONTENTS
PageNo.
1.0introduction4
2.0safety&environmental5
3.0material&Consumables7
4.0systempreparation7
4.1ProductionWellhead9
4.2TestSeparator&WellStart-UpPump10
4.3ElectricalTestSeparatorHeater12
4.4PigLauncher&PigReceiver13
4.5ChemicalInjection14
4.6WaterInjection15
4.7ClosedDrain16
4.8OpenDrain17
APPENDICES
Appendixa–WGPA-markedupp&IDs19
Appendixb–recordformforpurgingsystem20
1.0introduction
ThepurposeofPhaseIIofthestart-upistoensurethatallsystempreparationiscarriedoutpriortoCFD11Field1stOilStart-Up.Themaintasksunderthisphaseofthestart-upareasfollows:
PhaseIIofthestart-upinitiallyinvolvesopeningthetreevalvesandtheselfequalisingSCSSVonwellWCP-1001.Theslugofasphaltenedispersantandcorrosioninhibitorwillminimisethepotentialofconcretionformationonstart-upaswellasminimisingthepressuredropacrosstheproductionchokewhenthewellisbroughtintoservice.Afterthisphaseiscompletethewellwillbelinedoutreadyforproductionwithpressurebeingheldagainsttheproductionchokevalves.
Thestartingbasisforthisphaseisthatallsafetysystemstogetherwiththoseutility/chemicalsystemsrequiredforpreparationoftheWGPAsystemareoperational.ThesearedefinedinSection4.0.
Thefirstwellintoproductionisahighwatercutwellandwillbeusedtostarttheplatformproductionandassistinequipmentwarmup.
ThetimingofPhaseIIcanbecompletedasaparallelactivitywiththeinitialPhaseIII-WHPAsystemspreparationandPhaseIV-FPSOsystemspreparationcheckspriortostart-up.Additionally,theprimingofasphaltenedispersant,waxinhibitorandcorrosioninhibitorlinesinthisprocedurecanbecarriedoutinparallel.Thesethreephasesshouldbeplannedsuchthatoncetheasphaltenedispersantinjectionlineshavebeenprimedandpressurized,WP-1001productioncancommence.Corrosioninhibitorisnotcriticalatthispoint,duringinitialproductionofWCP-1001,thecorrosioninhibitorlinescanstillbeprimedreadyforcorrosioninhibitorinjection.
Shutdownsignalsthatrequiretobeoverriddenaspartofthestart-upwillbeimplementedthroughtheFoxboroSoftwareusingtheStart-UpTimerOverridefacility.Signalsoverriddenthiswaywillautomaticallybecomeoperationalwhena‘healthy’signal(i.e.abovethetripset-point)isreceived.Thismethodautomaticallyoverridestheoutputfromthetransmittertopreventthetripactionsfrombeingexecuted.ThereforewhereatransmitterhasaHiHiandLoLotripassociatedwithit,theHiHitripwillremainoperational.
PhaseIIofthestart-upprepareWGPA’ssafety&environmentsystemsforstart-Upandensuresthestatusofprocesssystemsandutilitysystemspreparationpriortofirstoil.
Firstoilsystemswillhavebeenhandovertooperations,operationswillleadthesystempreparation.
Allutilitiesandancillaries(includingflare,drains,andheatingmedium,powerandinstrumentcontrol/safetysystems)whicharerequiredbytheaboveprocessingfacilitieswillbefullycommissionedandavailable.
OncompletionofPhaseII,WGPAwillbereadytocommencefirstoilstart-Up.
2.0safety&environmental
ManagingSafetyandcarefortheEnvironmentisthefirstpriorityfortheprojectteam.Allofthestartupactivitieswillberequiredtofullyconsider;thesafetyandhealthhazards,plusanypotentialforunwanteddischargestothesea.Allworkwillbesubjecttoriskassessmentandpersonnelwillbemadeawareofanypotentialhazards.ThroughfullyunderstandingtheworkscopeandcarefullymanagingtheHazardstheprojectteamexpecttocarryouttheprogramefficientlyandsafely.
PriortoStartup,alloftheLifesaving,CommunicationsandEmergencyResponsesystemswillhavebeenfullycommissionedandhandedovertotheoperationsteam.Thiswillhavebeendocumentedinthecommissioninghandoverreports.Personnelinvolvedinthestartupwillberequiredtofullyunderstandtheescapeplantheymayberequiredtoundertake.
FurthertotheLifesavingandEmergencyResponsesystemsthefollowingcontrol,safetyandfirefightingsystemswillbeoperational:
–EmergencyShutdownSystem(ESD)
–ProcessControlSystem(PCS)
–FireandGasDetection(F&G)
–Firewaterprotectionsystems,monitors,deluge,foam,CO2systems&fireextinguishers.
–Flare&VentSystems,PSVs
–Localsafetyshowers,EyeWashStations.
Alloftherelevanthandoveracceptancedocumentationwillbecompleteandavailable.
TocommencethisphaseoftheCFD11FieldStart-Up,approvalisrequiredbytheFieldOIMandWellheadSupervisors.
AllactivitiesduringthisphaseshallbesubjecttotheappropriateriskassessmentandtheworkwillbecarriedoutinaccordancewiththePermittoWorkSystem.
Priortostartup,allotherworkactivities,suchastopsidesconstruction,drilling,wellcompletion,marine,loading,liftingandcommissioningshallbereviewedtoestablishiftheareanyconflicts.Wherenecessaryotherworkwillceaseuntilitisconsideredsafetodoso.Allhotworkactivitywillberequiredtoceaseinhighriskareas
Alloutstandingactionsfromtheprojectorstart-upprocedureHAZOPs/HAZIDsshouldbereviewedandallcriticalissuesclosedandsignedoff.
AnyblindsorspadesusedtoprovidephysicalisolationmustbeidentifiableaccordingtoCFD11-1/2oilfieldisolationphilosophy.
Safetyreviews/talkswillhavebeencompletedwithallrelevantpersonnelpriortocommencingthisphaseofpreparationforfirstoil.ThisshallbedocumentedusingaToolBoxRecordsheet.
Thecorrectandmarkedupdocumentationwillbemadeavailabletotheappropriatepersonnelinvolvedinthestartupactivity.
Platformandpersonalcommunicationsystemswillbetestedpriortostartup.Regularannouncements/communicationswillbemaintainedtoadvisepersonnelofthestartupprogressandanysafetyissues.
Asystemwillbeinplacetomanagechangestothestartupplan.Thiswillincludethenecessaryconsideration/riskassessmentbyallrelevantparties.Changestotheprogramwillincludenecessarychangestodocumentationandfurthertoolboxtalksforallpersonnelinvolved.
3.0material&Consumables
Thefollowingmaterials/consumableswillbeutilisedduringStart-Up.
1)Theasphaltenedispersantandwaxinhibitorinjectionlineswillrequirebeingprimedwithasphaltenedispersantandwaxinhibitorpriortofirstoilstart-up.
2)Thecorrosioninhibitorinjectionlineswillrequirebeingprimedwithcorrosioninhibitorpriortofirstoilstart-up.
3)Diesel.Thedieselequalizationlineswillrequirebeingprimedwithdieselpriortofirstoilstartup.AdequatedieselsuppliesshouldbeonboardforwellequalizationPhaseVI-WGPAProductionStart-Up.
4.0systempreparation
AllsystemsaredetailedinSection3.0ofPhaseI–HandovertoOperations(DocumentNo.CFD-OP-PR-001)arerequiredandshouldalreadybeoperationalaspartofthepre-requisitetotheCFD11-1/2oilfieldstart-upphase.
CFD11-1/2oilfieldsystemshavebeenhandedovertooperations.Theworkforwellcompletionandinducedproductionhasbeenfinished.Theutilitysystemandprocesssystemsstatusshouldbeconfirmed.Butalltheutilitiessystemhasbeenstarteduporinservice.Theutilitiessystemdetailscanbeshownasfollowings:
1)Firewater,delugeandfoamsystemsfunctioningandlive.
2)AllSCSSV’sandSSV’sfunctiontestedandoperationalfromtheWellheadLocalControlPanelfortheproductionwellstobecommissioned.
3)Allancillaries(e.g.airandpower)requiredforthewellheadlocalControlPanelfortheproductionwellstobecommissioned.
4)ESDsystemliveandfunctioningwithrequiredlinkstothewellheadlocalControlPanel.
5)Fire&Gassystemliveandfunctioning.
6)AsphaltenedispersantinjectionsystemcommissionedandavailabletoinjectviaXmastreeforthoselinestobestartedup.Anadequatevolumeofasphaltenedispersantmustalsobeavailableinthestoragetank(championtoadvise).
7)CorrosioninhibitorsystemcommissionedandavailabletoinjectviaXmastreeforthoselinestobestartedup.
8)Waxinhibitorinjectionsystemcommissionedandavailabletoinjectviaproductionlinedownstreamlinestobestartedup.Anadequatevolumeofwaxinhibitormustalsobeavailableinthestoragetank.
9)Closeddrain/ventscrubbervesselnormaloperationlevelestablishedandcloseddrainpumpscommissioned.
10)TheClosedDrainssystemavailable.
11)OpenDrainssystemavailable.
12)Seawatersystemoperational.
13)Dieselsystemoperationalandlinedouttotheusers.
14)Potablewatersystemoperationalandlinedouttotheusers.
15)PowersystemisbeingsuppliedfromFPSO.
16)Emergencygeneratoravailable.
17)UPSavailableandfunctioning.
ObtainclearancefromtheOIMandProductionSupervisortocommencePhaseII-WGPAPreparationforFirstOil.EnsurepermitsareavailableforPhaseIIwork.EnsurethatradiocommunicationsexistbetweentechniciansinthefieldandthecentralControlRoom(CCR).
Theprocesssystemwillseparatelybecarriedoutpreparationdetai