Moderate
3.Aggregateplanningsolvesproblemsinvolvingaggregatedecisionsratherthanstockkeepingunit(SKU)leveldecisions.
4.Traditionally,muchofaggregateplanningisfocusedwithinanenterpriseandmaynotalwaysbeseenasapartofsupplychainmanagement.
5.Aggregateplanningisanimportantsupplychainissuebecause,tobeeffective,itrequiresinputsfromthroughoutthesupplychain,butitsresultshavelittleimpactonthesupplychain.
6.Short-termproductionservesasabroadblueprintforoperationsandestablishestheparameterswithinwhichaggregateplanningdecisionsaremade.
7.Theaggregateplanningproblemisconcernedwithdeterminingtheproductionlevel,inventorylevel,andcapacitylevel(internalandoutsourced)foreachperiodthatmaximizesthefirm’sprofitovertheplanninghorizon.
8.Tocreateanaggregateplan,acompanymustspecifytheplanninghorizonfortheplanandthedurationofeachperiodwithintheplanninghorizon.
9.Aplanninghorizonisusuallybetweenthreeandfiveyears.
10.Apooraggregateplancanresultinimprovedsalesandprofitsiftheavailableinventoryandcapacityareunabletomeetdemand.
11.Apooraggregateplanmayresultinalargeamountofexcessinventoryandcapacity,therebyraisingcosts.
True
12.Theaggregateplannermustmakeatrade-offbetweencapacity,inventory,andbacklogcosts.
13.Anaggregateplanthatincreasesonecosttypicallyresultsintheincreaseoftheothertwo.
14.Thetimeflexiblestrategyiswheretheproductionrateissynchronizedwiththedemandratebyvaryingmachinecapacityorhiringandlayingoffemployeesasthedemandratevaries.
Hard
15.Thetimeflexiblestrategyiswhereworkforce(capacity)iskeptstablebutthenumberofhoursworkedisvariedovertimeinanefforttosynchronizeproductionwithdemand.
16.Themixedstrategyiswhereastablemachinecapacityandworkforcearemaintainedwithaconstantoutputratewithinventorylevelsfluctuatingovertime.
17.Moststrategiesthatanaggregateplanneractuallyusesareincombination,andarereferredtoasmixedstrategies.
18.Ahighlyeffectivetoolforacompanytousewhenittriestomaximizeprofitswhilebeingsubjectedtoaseriesofconstraintsisaggregateprogramming.
19.Toimprovethequalityoftheseaggregateplans,forecasterrorsmustbetakenintoaccountwhenformulatingaggregateplans.
20.Forecastingerrorsaredealtwithinaggregateplansusingeithersafetybacklogorsafetycapacity.
21.Safetyinventoryisdefinedasinventoryheldtosatisfydemandthatishigherthanforecasted.
22.Safetycapacityisdefinedascapacityusedtosatisfydemandthatislowerthanforecasted.
23.Companiesshouldworkwithdownstreampartnerstoproduceforecastsandwithupstreampartnerstodetermineconstraintswhendoingaggregateplanning.
24.Theaggregateplanshouldbeviewedprimarilyasanin-housetoolthatdoesnotneedtobecommunicatedtosupplychainpartners.
25.Giventhatforecastsarealwayswrongtosomedegree,theaggregateplanneedstohavesomeflexibilitybuiltintoitifitistobeuseful.
26.Amanagershouldperformsensitivityanalysisontheinputsintoanaggregateplantochoosethebestsolutionfortherangeofpossibilitiesthatcouldoccur.
27.Asinputsintotheaggregateplanchange,managersdonotneedtomakechangestotheaggregateplan.
28.Ascapacityutilizationincreases,itbecomeslessimportanttoperformaggregateplanning.
MultipleChoice
1.Theprocessbywhichacompanydetermineslevelsofcapacity,production,subcontracting,inventory,stockouts,andevenpricingoveraspecifiedtimehorizonis
a.aggregateplanning.
b.detailplanning.
c.inventoryplanning.
d.salesplanning.
e.alloftheabove
a
2.Thegoalofaggregateplanningisto
a.dissatisfycustomersinawaythatmaximizesprofit.
b.dissatisfycustomersinawaythatminimizesprofit.
c.satisfydemandinawaythatmaximizesprofit.
d.satisfydemandinawaythatminimizesprofit.
e.noneoftheabove
c
3.Aggregateplanningsolvesproblemsinvolving
a.aggregatedecisionsandstockkeepingunit(SKU)leveldecisions.
b.aggregatedecisionsorstockkeepingunit(SKU)leveldecisions.
c.aggregatedecisionsratherthanstockkeepingunit(SKU)leveldecisions.
d.stockkeepingunit(SKU)leveldecisionsratherthanaggregatedecisions.
e.bandconly
4.Aggregateplanning,tobeeffective,requiresinputsfrom
a.allcustomers.
b.alldepartments.
c.allsuppliers.
d.throughoutthesupplychain.
e.throughoutthecompany.
d
5.Muchofaggregateplanninghastraditionallybeenfocused
a.onshort-termproductionscheduling.
b.oncustomerrelationshipmanagement.
c.withinanenterprise.
d.beyondenterpriseboundaries.
6.Whichofthefollowingarenotoperationalparameterstheaggregateplannerisconcernedwith?
a.productionrate
b.workforce
c.overtime
d.backorders
e.inventoryonhand
7.Theoperationalparameterconcernedwiththenumberofunitscompletedperunittime(suchasperweekorpermonth)is
a.productionrate.
b.workforce.
c.overtime.
d.backlog.
e.inventoryonhand.
8.Theoperationalparameterconcernedwiththenumberofworkers/unitsofcapacityneededforproductionis
b
9.Theoperationalparameterconcernedwiththeamountofovertimeproductionplannedis
10.Theoperationalparameterconcernedwithdemandnotsatisfiedintheperiodinwhichitarises,butcarriedovertofutureperiodsis
11.Theoperationalparameterconcernedwiththeplannedinventorycarriedoverthevariousperiodsintheplanninghorizonis
e
12.Theoperationalparameterconcernedwiththenumberofunitsofmachinecapacityneededforproductionis
a.machinecapacitylevel.
b.subcontracting.
13.Theoperationalparameterconcernedwiththesubcontractedcapacityrequiredovertheplanninghorizonis
14.Theaggregateplan
a.servesasabroadblueprintforoperations.
b.establishestheparameterswithinwhichshort-termproductionanddistributiondecisionsaremade.
c.allowsthesupplychaintoaltercapacityallocationsandchangesupplycontracts.
d.alloftheabove
15.Aggregateplanningisconcernedwithdetermining
a.theproductionlevel,saleslevel,andcapacityforeachperiod.
b.thedemandlevel,inventorylevel,andcapacityforeachperiod.
c.theproductionlevel,inventorylevel,andcapacityforeachperiod.
d.theproductionlevel,staffinglevel,andcapacityforeachperiod.
16.Tocreateanaggregateplan,acompanymustspecify
a.theplanninghorizonfortheplan.
b.thedurationofeachperiodwithintheplanninghorizon.
c.keyinformationrequired.
e.aandbonly
17.Theplanninghorizonis
a.thetimeperiodoverwhichtheaggregateplanistoproduceasolution.
b.thedurationofeachtimeperiodintheaggregateplan.
c.thelengthoftimerequiredtoproducetheaggregateplan.
d.thesolutiontotheaggregateplan.
18.Thelengthoftheplanninghorizonisusuallybetween
a.oneandthreemonths.
b.threeandeighteenmonths.
c.oneandthreeyears.
d.threeandfiveyears.
19.Whichofthefollowingisnotinformationneededbytheaggregateplanner?
a.demandforecastforeachperiodintheplanninghorizon
b.productioncosts
c.laborcosts
d.costofsubcontractingproduction
e.costofchanging